General Information
- The measurements must be performed using the insulation tester Insulation tester WE 1379 .
- A measuring voltage of 500 V must be selected.
- To obtain the required measuring resistance, the measuring voltage must be present on the insulation tester for at least 1 second .
- The tolerance range is +/- 10% .
- Two measurements must always be performed for each measuring point. Positive terminal on shielding and negative terminal on shielding.
- A measurement is only regarded as being within the tolerance range if both measured values are within the tolerance range.
- The direction of measurement of the insulation tester does not affect the test result.
- The measured values must be documented in the "Insulation fault finding test log". The test log is stored under Standard forms in the PIWIS information system.
- A complete overview of all high-voltage components is available in the high-voltage safety system plan. The high-voltage safety system plan is stored under Standard documents in the PPN.
- A complete overview of all measuring points can be found in the measuring point overview. The measuring point overview is stored under Standard forms in the PIWIS information system.