Removal and Installation: Installation
WARNING: This page is about a different car, the 2018 Nissan Maxima. However, it is still accessible from the selected car via links, so may be relevant.
- Install new O-rings to water pump (1).CAUTION: Do not reuse O-rings.
- Apply engine oil to the O-rings (2, 3) as shown.
- Locate the O-ring (2) with white paint mark (A) to engine front side.
- Hold timing chain to the side (
) and install the water pump (
).
CAUTION:- Install water pump without causing sprocket to contact timing chain. It may be necessary to adjust the timing chain until it loosens enough to install the water pump.
- Install water pump straight in while preventing vane from contacting the engine block and timing chain case.
- Be careful not to damage the O-rings when installing the water pump.
- Check that timing chain and water pump sprocket are engaged.
- Tighten water pump bolts alternately and evenly to specification.
- Remove dust and foreign material completely from installation area of timing chain tensioner and rear timing chain case.
- Turn the crankshaft pulley approximately 20° clockwise so that the timing chain on the timing chain tensioner side is loose.
- Apply engine oil to the oil feed hole and timing chain tensioner and install the timing chain tensioner.
- Remove the stopper pin (A).
- Install valve timing control cover (bank 1) and water pump cover.
- Before installing, remove all traces of liquid gasket from mating surface of water pump cover and IVT cover using a scraper.
Also remove traces of liquid gasket from the mating surface of the front cover.
- Using Genuine RTV Silicone Sealant or equivalent, apply a continuous bead of liquid gasket to mating surface of IVT cover and water pump cover. Refer to Recommended Chemical Products and Sealants
.CAUTION:
- Installation should be done within 5 minutes after applying liquid gasket.
- Do not fill the engine with oil for at least 30 minutes after the components are installed to allow the sealant to cure.
- Before installing, remove all traces of liquid gasket from mating surface of water pump cover and IVT cover using a scraper.
- Installation of remaining components is in the reverse order of removal.
- After installation, refill coolant and check for leaks. Refer to Changing Engine Coolant and System Inspection .CAUTION: Do not spill coolant in engine compartment. Use a shop cloth to absorb coolant.
- After starting engine, let idle for three minutes, then rev engine up to 3, 000 RPM
no-load to purge air from the high-pressure chamber of the chain tensioner. The engine may produce a rattling noise. This indicates that air still remains in the chamber and is not a matter of concern.
- After installation, refill coolant and check for leaks. Refer to Changing Engine Coolant and System Inspection .