Component Function Check
WARNING: This page is about a different car, the 2018 Nissan Titan XD and 2018 Nissan Titan. However, it is still accessible from the selected car via links, so may be relevant.
- PRECONDITIONING
TESTING CONDITION:
- Before performing the following procedure, confirm that battery voltage is 12.8 V or more at idle.
- Before performing the following procedure, confirm that all load switches and A/C switch are turned OFF.
GO TO 2 .
- PERFORM COMPONENT FUNCTION CHECK
WITH CONSULT
- Start engine and let it idle.
- Select "BAT CUR SEN" in "DATA MONITOR" mode with CONSULT.
- Check "BAT CUR SEN" indication for 10 seconds.
"BAT CUR SEN" should be above 2, 300 mV at least once.
WITHOUT CONSULT
- Start engine and let it idle.
- Check the voltage between ECM harness connector terminals as per the following.
ECM
Voltage (V)
Connector
+
-
Terminal
Terminal
F78
38
(Battery current sensor signal)
43
Approx. 2.5
Is the inspection result normal?
YES
INSPECTION END
NO
Go to Diagnosis Procedure .