Total Preload

  1. Measure pinion bearing preload torque (P1). Refer to "PRELOAD TORQUE ".
  2. Install the pinion sleeve shims and pinion sleeve assembly.
  3. Rotate the companion flange at least 20 times to check for smooth operation of the bearing.
  4. Measure the total preload with the preload gauge (A) [SST: ST3127S000 (J-25765-A)].

    Standard 

    Total Preload torque : Refer to  "PRELOAD TORQUE ".

    CAUTION: Preload torque differs before disassembly and after reassembly.
Fig 1: Measuring Total Preload With Preload Gauge
G05892806Courtesy of NISSAN MOTOR CO., U.S.A.