Home >> Nissan-Datsun >> 2009 >> Murano LE >> Repair and Diagnosis >> Drivelines & Axles >> Driveshaft & Universal Joints >> Transfer Case, Rear Propeller Shaft & Rear Final Drive >> Rear Final Drive: R145 >> Disassembly And Assembly >> Drive Pinion >> Adjustment >> Total Preload Torque

Total Preload Torque

  1. Remove electric controlled coupling assembly. Refer to "DISASSEMBLY ".
  2. Rotate drive pinion back and forth 2 to 3 times to check for unusual noise and rotation malfunction.
  3. Rotate drive pinion at least 20 times to check for smooth operation of the bearing.
  4. Fit drive pinion socket onto drive pinion spline. Measure the total preload, using the preload gauge (A) [SST: 3127S000 (J-27565- A)] and drive pinion socket (B) [SST: KV38108500 -)].

    Standard 

    Total preload torque : Refer to  "PRELOAD TORQUE ".

Fig 1: Fitting Drive Pinion Socket Onto Drive Pinion Spline
G04921369Courtesy of NISSAN MOTOR CO., U.S.A.
NOTE: Total preload torque = Pinion bearing torque + Side bearing torque