LEMON Manuals: Even more car manuals for everyone
Home >> Nissan-Datsun >> 2004 >> Altima S, Standard >> Repair and Diagnosis >> External Pages >> Different car >> Section 1019 (Charging System) >> Component Diagnosis >> Charging System Preliminary Inspection >> Inspection Procedure

Inspection Procedure

WARNING: This page is about a different car, the 2009 Nissan Maxima. However, it is still accessible from the selected car via links, so may be relevant.
  1. CHECK BATTERY TERMINALS CONNECTION

    Check if battery terminals are clean and tight.

    Is the inspection result normal? 

    YES: GO TO 2

    NO: Repair battery terminals connection.

  2. CHECK FUSE

    Check for blown fuse and fusible link.

    FUSE AND FUSIBLE LINK REFERENCE

    Unit Power source (Power supply terminals) Fuse or Fusible Link
    Generator Battery (terminal 3) Fuse 29
    Battery (terminal 1) Fusible Link A
    Combination meter Ignition switch ON (terminal 2) Fuse 4

    Is the inspection result normal? 

    YES: GO TO 3

    NO: Be sure to eliminate cause of malfunction before installing new fuse or fusible link.

  3. CHECK GENERATOR GROUND TERMINAL CONNECTION

    Check if connector E230 terminal 5 (generator ground harness) is clean and tight.

    Is the inspection result normal? 

    YES: GO TO 4

    NO: Repair connection.

  4. CHECK DRIVE BELT TENSION

Check drive belt tension. Refer to "INSPECTION ".

Is the inspection result normal? 

YES: Inspection End.

NO: Repair as needed.