Installation (Upper)
WARNING: This page is about a different car, the 2007 Nissan Pathfinder. However, it is still accessible from the selected car via links, so may be relevant.
- Install oil pan (upper) as follows:
- Use scraper to remove old liquid gasket from mating surfaces.
- Also remove the old liquid gasket from mating surface of lower cylinder block.
- Remove old liquid gasket from the bolt holes and threads.
CAUTION: Do not scratch or damage the mating surfaces when cleaning off old liquid gasket. - Install new O-rings on the bottom of lower cylinder block and oil pump.
- Apply a continuous bead of liquid gasket using Tool to the lower cylinder block mating surfaces of oil pan (upper) to a limited portion as shown above.
Tool number : WS39930000 (-)
Use Genuine RTV Silicone Sealant or equivalent. Refer to "RECOMMENDED CHEMICAL PRODUCTS AND SEALANTS ".
CAUTION:- For bolt holes with mark, apply liquid gasket outside the hole.
- Apply a bead of 4.5 to 5.5 mm (0.177 to 0.217 in) in diameter to area "A".
- Attaching should be done within 5 minutes after coating.
- Install oil pan (upper).CAUTION: Install avoiding misalignment of both oil pan gaskets and O-rings.
- Tighten bolts in numerical order as shown below.
- There are two types of bolts. Refer to the following for locating bolts.
M8 x 100 mm (3.97 in) : 7, 11, 12, 13
M8 x 25 mm (0.98 in) : Except the above
- Tighten transmission joint bolts. Refer to "TRANSMISSION ASSEMBLY ".
- Use scraper to remove old liquid gasket from mating surfaces.
- Install oil strainer to oil pan (upper).
- Installation of the remaining components is in the reverse order of removal.