Prepare A-Pillar Outer Section For Installation - Ar63.20-P-1102-02LW

Model 205.0/1/2 

Model 253 

IMPORTANT The following steps are shown on the left side of the vehicle and must be performed analogously on the right side in the event of damage.

  1. Mark separating point on A-pillar paneling (5) and cut (areas A and B).

    IMPORTANT Transfer separation points from vehicle.

  2. Grind mating surfaces on A-pillar paneling (5) down to bare metal in crosshatched areas.

    IMPORTANT Sand down spot weld flanges to bare metal on both sides.

    IMPORTANT Model 205.0/1/2

    Grind mating surfaces down to bare metal on inside (area C).

  3. Remove grinding dust.
  4. Coat insides of spot weld flanges with zinc dust paint.

    NOTES Model 205.0/1/2

    Do not coat bonding surfaces with zinc dust paint (area C).

    Otherwise adhesion problems may occur.

    IMPORTANT Observe pretreatment of bonding surfaces.

    Fig 1: A-Pillar Installation Preparation Cut Line Locations (Model 205.0/1/2 & 253)
    G12824107Courtesy of MERCEDES-BENZ USA
  5. Mark separating point on A-pillar reinforcement (6) and cut (areas D and E).

    IMPORTANT Transfer separation points from vehicle.

  6. Cut water drain hose from A-pillar reinforcement section.
    Fig 2: A-Pillar Reinforcement Installation Preparation Cut Line Locations (Model 205.0/1/2 & 253)
    G12824108Courtesy of MERCEDES-BENZ USA
    G12824109Courtesy of MERCEDES-BENZ USA
  7. Grind mating surfaces on A-pillar reinforcement (6) down to bare metal in cross-hatched areas.

    IMPORTANT Sand down spot weld flanges to bare metal on both sides.

  8. Remove grinding dust.
  9. Coat insides of spot weld flanges with zinc dust paint.

    NOTES Do not coat bonding surfaces with zinc dust (areas F). Otherwise adhesion problems may occur.

    IMPORTANT Observe pretreatment of bonding surfaces.

    Fig 3: Inner A-Pillar Installation Preparation Cut Line Locations (Model 205.0/1/2 & 253)
    G12824110Courtesy of MERCEDES-BENZ USA
  10. Mark separating points on A-pillar inner panel (7) and cut (areas G and H).

    IMPORTANT Transfer separation points from vehicle.

  11. Expose spot welds on A-pillar inner panel (7) and cut out (areas I).
  12. Expose spot welds on A-pillar inner panel (7) and drill with Ø 6.5 mm bit (area J).
  13. Grind mating surfaces on A-pillar inner panel (7) down to bare metal in crosshatched areas.

    IMPORTANT Sand down spot weld flanges to bare metal on both sides.

  14. Remove grinding dust.
  15. Coat insides of spot weld flanges with zinc dust paint.

    NOTES Do not coat bonding surfaces with zinc dust paint (areas K).

    Otherwise adhesion problems may occur.

    IMPORTANT Observe pretreatment of bonding surfaces.

G12824111Courtesy of MERCEDES-BENZ USA