Notes regarding installation of trailer hitch - AH31.10-P-1000-02SX

Model 221 

IMPORTANT The control cable must be hung in the operating lever before the transport lock between the crossmember and swivel ball neck is removed. Otherwise the system locks and cannot be unlocked.

The ball neck snaps into its two end positions and can only be operated using the cable at the release lever. 

Fig 1: View Of Transport Lock
G07507094Courtesy of MERCEDES-BENZ USA

IMPORTANT In export countries the respective licensing provisions or legal requirements for the installation of a trailer hitch must be observed.

IMPORTANT The body sealing compound and underbody sealant must be removed from all the body mounting points of the trailer coupling. The mounting points should then be cleaned with a commercially available cleaning agent. Apply anticorrosion paint to bare-metal areas of the body.

IMPORTANT Trailer couplings are homologated safety parts. Their installation on the vehicle is to be carried out exclusively by trained, professional technicians. Trailer couplings, which are damaged because of an accident, bottoming or being run into from behind, must be replaced; subsequent alterations such as bending, mechanically processing, and welding are not permitted.

NOTESThe diameter of the coupling ball, measured with a caliper gauge, must measure at least 49 mm at all points. The ball must be greased before use to reduce wear. Advise the customer accordingly. 

IMPORTANT It not necessary to grease the ball on trailers with an anti-swerve device (refer to trailer instructions). Advise the customer accordingly.

IMPORTANT Advise the customer to read the "Trailer coupling" and "Towing a trailer" sections in the vehicle owner's manual.

IMPORTANT The customer should be recommended to install a battery with a larger capacity (at least 70Ah).