Airflow inspection (Except U.S.A. And CANADA)
WARNING: This page is about a different variant/trim than selected.
- Perform the following procedure to verify the charcoal canister airflow. (Between port A and port C)
- Plug the port B.
- Apply a pressure of 0.98 kPa {7.4 mmHg, 0.29 inHg} to port A.
- Verify that there is airflow from port C.
- If there is no airflow, replace the charcoal canister. (See CHARCOAL CANISTER REMOVAL/INSTALLATION .)
- Plug the port B.
- Perform the following procedure to verify the charcoal canister airflow. (Between port B and port C)
- Plug the port A.
- Apply a pressure of 0.98 kPa {7.4 mmHg, 0.29 inHg} to port C.
- Verify that there is airflow from port B.
- If there is no airflow, replace the charcoal canister. (See CHARCOAL CANISTER REMOVAL/INSTALLATION .)
- Plug the port A.