Diagnostic Procedure
| STEP | INSPECTION | ACTION | |
|---|---|---|---|
| 1 | VERIFY RELATED REPAIR INFORMATION AVAILABILITY
|
Yes | Perform repair or diagnosis according to the available repair information.
|
| No | Go to the next step. | ||
| 2 | INSPECT BATTERY
|
Yes | Recharge or replace the battery, then go to Step 7. (See BATTERY RECHARGING [MZR 2.5] .) (See BATTERY REMOVAL/INSTALLATION [MZR 2.5] .) |
| No | Go to the next step. | ||
| 3 | INSPECT POOR INSTALLATION OF GENERATOR TERMINAL
|
Yes | Tighten the generator terminal B installation nut, then go to Step 7. |
| No | Go to the next step. | ||
| 4 | INSPECT POOR INSTALLATION OF BATTERY POSITIVE TERMINAL
|
Yes | Connect the battery positive terminal correctly, then go to Step 7. |
| No | Go to the next step. | ||
| 5 | INSPECT BATTERY CHARGING CIRCUIT FOR SHORT TO GROUND OR OPEN CIRCUIT
|
Yes | Go to the next step. |
| No | Inspect the MAIN ST 250 A fuse.
Go to Step 7. |
||
| 6 | INSPECT GENERATOR
|
Yes | Repair or replace the malfunctioning part according to the inspection results, then go to the next step. (See GENERATOR DISASSEMBLY/ASSEMBLY [MZR 2.5] .) (See GENERATOR REMOVAL/INSTALLATION [MZR 2.5] .) |
| No | Go to the next step. | ||
| 7 | VERIFY DTC TROUBLESHOOTING COMPLETED
|
Yes | Repeat the inspection from Step 1.
Go to the next step. |
| No | Go to the next step. | ||
| 8 | VERIFY AFTER REPAIR PROCEDURE
|
Yes | Go to the applicable DTC inspection. (See DTC TABLE .) |
| No | DTC troubleshooting completed. | ||