Diagnostic Procedure
| STEP | INSPECTION | ACTION | |
|---|---|---|---|
| 1 | PERFORM PCM DTC INSPECTION
|
Yes | Go to the applicable DTC inspection. (See DTC TABLE [MZR 2.5] .) |
| No | Go to the next step. | ||
| 2 | INSPECT BATTERY
|
Yes | Recharge or replace the battery, then go to Step 6. (See BATTERY RECHARGING [MZR 2.5] .) (See BATTERY REMOVAL/INSTALLATION [MZR 2.5] .) |
| No | Go to the next step. | ||
| 3 | INSPECT GENERATOR
|
Yes | Replace the generator, then go to Step 6. (See GENERATOR REMOVAL/INSTALLATION [MZR 2.5] .) |
| No | Go to the next step. | ||
| 4 | INSPECT INSTRUMENT CLUSTER CONNECTOR AND TERMINALS
|
Yes | Repair or replace the connector or terminals, then go to Step 6. |
| No | Go to the next step. | ||
| 5 | INSPECT INSTRUMENT CLUSTER POWER SUPPLY CIRCUIT FOR OPEN CIRCUIT AND SHORT TO GROUND
|
Yes | Go to the next step. |
| No | Inspect the ROOM 15 A fuse and METER 10 A fuse. If the fuse is blown:
|
||
| 6 | VERIFY TROUBLESHOOTING COMPLETED
|
Yes | Repeat the inspection from Step 1.
Go to the next step. |
| No | Go to the next step. | ||
| 7 | VERIFY THAT NO OTHER DTCs ARE PRESENT
|
Yes | Go to the applicable DTC inspection. (See DTC TABLE [INSTRUMENT CLUSTER] .) |
| No | DTC troubleshooting completed. | ||