  1. Install the intake manifold.

    Tightening torque 

    17-23 N.m {1.8-2.3 kgf.m, 13-16 ft.lbf} 

    Fig 1: Wastegate Control Solenoid, Hoses & Torque Specification
    G04324736Courtesy of MAZDA MOTORS CORP.
  2. Install the vacuum hose.
  3. Install the drive belt.
  4. Install the oil level gauge pipe. (See OIL PAN REMOVAL/INSTALLATION ).
  5. Install the fuel delivery pipe cover in the order in the figure.

    Tightening torque 

    17-23 N.m {1.8-2.3 kgf.m, 13-16 ft.lbf} 

  6. Install the high pressure fuel pump bracket and the EGR pipe bracket.
    Fig 2: High Pressure Fuel Pump & EGR Bracket
    G04324737Courtesy of MAZDA MOTORS CORP.