Installation [09/2014 - 11/2017]: Procedure
- INSTALL NO. 2 COOLING FAN MOTOR
- Install the No. 2 cooling fan motor with the 3 screws.
Torque: 2.6 N.m (27 kgf/cm, 23 in.lbf)
- Install the No. 2 cooling fan motor with the 3 screws.
- INSTALL COOLING FAN MOTOR
- Install the cooling fan motor with the 3 screws.
Torque: 3.9 N.m (40 kgf/cm, 35 in.lbf)
- Install the cooling fan motor with the 3 screws.
- INSTALL FAN NOTE:
Do not reverse the position of the fan and No. 2 fan when installing them. Doing so may damage the parts.
- Install the fan with the nut.
Torque: 6.3 N.m (64 kgf/cm, 56 in.lbf)
- Install the fan with the nut.
- INSTALL NO. 2 FAN NOTE:
Do not reverse the position of the fan and No. 2 fan when installing them. Doing so may damage the parts.
- Install the No. 2 fan with the nut.
Torque: 6.3 N.m (64 kgf/cm, 56 in.lbf)
- Install the No. 2 fan with the nut.
- INSTALL COOLING FAN ECU
- Install the cooling fan ECU with the 2 screws.
Torque: 2.6 N.m (27 kgf/cm, 23 in.lbf)
- Engage the 4 clamps.
- Connect the cooling fan motor connector and No. 2 cooling fan motor connector.
- Install the cooling fan ECU with the 2 screws.
- INSTALL FAN SHROUD ASSEMBLY
- Engage the 3 guides.
- Engage the 3 claws and install the fan shroud assembly to the radiator assembly.NOTE:
Do not damage the radiator assembly when installing the fan shroud assembly.
- INSTALL ENGINE ROOM ECU OUTLET DUCT
See step 4
- CONNECT ENGINE ROOM MAIN WIRE
See step 7
- INSTALL RADIATOR RESERVE TANK ASSEMBLY
See step 10
- INSTALL NO. 1 RADIATOR HOSE
See step 9
- INSTALL INLET NO. 1 AIR CLEANER
Refer to PROCEDURE - Step 86 [09/2014 - 10/2015] , or refer to PROCEDURE - Step 87 [10/2015 - 11/2017]
- ADD ENGINE COOLANT
See step 6 [09/2014 - 10/2015], or see step 6 [10/2015 - 11/2017]
- INSPECT FOR COOLANT LEAK
Refer to PROCEDURE - Step 1
- INSTALL NO. 1 ENGINE UNDER COVER ASSEMBLY
Refer to PROCEDURE - Step 116 [09/2014 - 10/2015] , or refer to PROCEDURE - Step 117 [10/2015 - 11/2017]
- INSTALL V-BANK COVER SUB-ASSEMBLY
Refer to PROCEDURE - Step 117 [09/2014 - 10/2015] , or refer to PROCEDURE - Step 118 [10/2015 - 11/2017]
- INSTALL COOL AIR INTAKE DUCT SEAL
Refer to PROCEDURE - Step 2
- INSTALL ENGINE ROOM SIDE COVER
Refer to PROCEDURE - Step 3