Installation [10/2015 - ]: Procedure
- INSTALL NO. 2 COOLING FAN MOTOR
- Install the No. 2 cooling fan motor with the 3 screws.
Torque: 3.9 N*m (40 kgf*cm, 35 in.*lbf)
- Engage the clamp.
- Connect the No. 2 cooling fan motor connector.
- Install the No. 2 cooling fan motor with the 3 screws.
- INSTALL COOLING FAN MOTOR
- Install the cooling fan motor with the 3 screws.
Torque: 3.9 N*m (40 kgf*cm, 35 in.*lbf)
- Engage the clamp.
- Connect the cooling fan motor connector.
- Install the cooling fan motor with the 3 screws.
- INSTALL NO. 2 FAN NOTE:
Do not reverse the position of the fan and No. 2 fan when installing them. Doing so may damage the parts.
- Install the No. 2 fan with the nut.
Torque: 6.3 N*m (64 kgf*cm, 56 in.*lbf)
- Install the No. 2 fan with the nut.
- INSTALL FAN NOTE:
Do not reverse the position of the fan and No. 2 fan when installing them. Doing so may damage the parts.
- Install the fan with the nut.
Torque: 6.3 N*m (64 kgf*cm, 56 in.*lbf)
- Install the fan with the nut.
- INSTALL COOLING FAN WIRE
- Connect the cooling fan wire connector.
- Engage the 3 clamps to install the cooling fan wire.
- INSTALL FAN SHROUD ASSEMBLY
- CONNECT NO. 2 RADIATOR HOSE SUB-ASSEMBLY
- Connect the No. 2 radiator hose sub-assembly to the fan shroud assembly with the bolt.
Torque: 5.0 N*m (51 kgf*cm, 44 in.*lbf)
- Install a new radiator hose clamp to the fan shroud assembly.
- Connect the No. 2 radiator hose sub-assembly to the radiator hose clamp.
- Connect the No. 2 radiator hose sub-assembly to the fan shroud assembly with the bolt.
- INSTALL RADIATOR HOSE SUB-ASSEMBLY
- INSTALL RADIATOR RESERVE TANK ASSEMBLY
- CONNECT ENGINE ROOM MAIN WIRE
- INSTALL ENGINE ROOM ECU OUTLET DUCT
See step 10 [10/2015 - 11/2017], or see step 10 [11/2017 - ]
- INSTALL INLET NO. 1 AIR CLEANER
Refer to PROCEDURE - Step 79
- ADD ENGINE COOLANT
See step 3
- INSPECT FOR COOLANT LEAK
Refer to PROCEDURE - Step 1
- INSTALL NO. 1 ENGINE UNDER COVER ASSEMBLY
Refer to PROCEDURE - Step 78
- INSTALL COOL AIR INTAKE DUCT SEAL
Refer to PROCEDURE - Step 2 [09/2014 - 11/2017] , or refer to PROCEDURE - Step 2 [11/2017 - 10/2018] , or refer to PROCEDURE - Step 2 [10/2018 - 10/2022] , or refer to PROCEDURE - Step 2 [10/2022 - ]
- INSTALL ENGINE ROOM SIDE COVER
Refer to PROCEDURE - Step 3 [09/2014 - 11/2017] , or refer to PROCEDURE - Step 3 [11/2017 - 10/2018] , or refer to PROCEDURE - Step 3 [10/2018 - 10/2022] , or refer to PROCEDURE - Step 3 [10/2022 - ]