Installation [11/2021 - 03/2022]: Procedure
WARNING: This page is about a different car, the 2025 Lexus NX 350h, 2024 Lexus NX 350h, 2023 Lexus NX 350h, and 2022 Lexus NX 350h. However, it is still accessible from the selected car via links, so may be relevant.
- INSTALL NO. 2 EXHAUST MANIFOLD HEAT INSULATOR
Torque: 11 N.m (112 kgf/cm, 8 ft.lbf)
- INSTALL EXHAUST MANIFOLD TO HEAD GASKET
- INSTALL EXHAUST MANIFOLD (TWC: Front Catalyst)
-
Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
*1 Exhaust Manifold (TWC: Front Catalyst) *2 No. 1 Exhaust Manifold Heat Insulator *3 No. 1 Front Floor Heat Insulator - - - Temporarily install the exhaust manifold (TWC: Front Catalyst), No. 1 exhaust manifold heat insulator and No. 1 front floor heat insulator.
HINT:
At this time, do not install the parts with bolts or nuts.
- Temporarily install the exhaust manifold (TWC: Front Catalyst) to the cylinder head sub-assembly with 7 new nuts.
- Tighten the 7 nuts in the order shown in the illustration.
Torque: 26 N.m (265 kgf/cm, 19 ft.lbf)
- Temporarily install the exhaust manifold (TWC: Front Catalyst), No. 1 exhaust manifold heat insulator and No. 1 front floor heat insulator.
-
- INSTALL FLOW SHUTTING VALVE (WATER BY-PASS HOSE ASSEMBLY)
Torque: 19 N.m (194 kgf/cm, 14 ft.lbf)
- INSTALL NO. 2 WATER BY-PASS PIPE SUB-ASSEMBLY
Torque: 19 N.m (194 kgf/cm, 14 ft.lbf)
- INSTALL MANIFOLD STAY
-
Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
- Temporarily install the manifold stay to the exhaust manifold (TWC: Front Catalyst) and cylinder block sub-assembly with the bolt and nut.
- Tighten the bolt and nut in the order shown in the illustration.
Torque: 43 N.m (438 kgf/cm, 32 ft.lbf)
-
- INSTALL NO. 1 FRONT FLOOR HEAT INSULATOR
Torque: 4.9 N.m (50 kgf/cm, 43 in.lbf)
- INSTALL NO. 1 EXHAUST MANIFOLD HEAT INSULATOR
Torque: 10 N.m (102 kgf/cm, 7 ft.lbf)
- INSTALL WIRING HARNESS CLAMP BRACKET
Torque: 13 N.m (133 kgf/cm, 10 ft.lbf)
- INSTALL AIR FUEL RATIO SENSOR (for Sensor 1)
Refer to INSTALLATION [11/2021 - ] - INSTALL COWL VENTILATOR PANEL SUB-ASSEMBLY
Refer to PROCEDURE - Step 17
- INSTALL COWL VENTILATOR SPLASH SHIELD LH
- INSTALL WINDSHIELD WIPER MOTOR AND LINK ASSEMBLY
Refer to INSTALLATION [11/2021 - ]
- INSTALL HOOD TO FRONT FENDER SEAL RH
- INSTALL HOOD TO FRONT FENDER SEAL LH
- INSTALL FRONT EXHAUST PIPE ASSEMBLY (TWC: Rear Catalyst)
Torque: 43 N.m (438 kgf/cm, 32 ft.lbf)
- INSPECT FOR EXHAUST GAS LEAK
Refer to INITIALIZATION [11/2021 - ]
- INSTALL ENGINE UNDER COVER HEAT INSULATOR
- INSTALL NO. 2 ENGINE UNDER COVER ASSEMBLY
Torque: 7.5 N.m (76 kgf/cm, 66 in.lbf)