Installation [11/2021 - ]: Procedure
- INSTALL FLOW SHUTTING VALVE (NO. 1 WATER BY-PASS HOSE)
Torque: 19 N.m (194 kgf/cm, 14 ft.lbf)
*a View A *b 90° *c Upper Side *d RH Side *e 2 to 7 mm (0.0787 to 0.276 in.) - - - Connect the flow shutting valve (No. 1 water by-pass hose) to the transmission oil cooler and slide the clip to secure it.NOTE:
- Make sure to slide the flow shutting valve (No. 1 water by-pass hose) until it contacts the hose stopper of the transmission oil cooler.
- Make sure that the tabs of the clip are within the area shown in the illustration.
- Connect the flow shutting valve (No. 1 water by-pass hose) to the transmission oil cooler and slide the clip to secure it.
*a View A *b 90° *c Upper Side *d RH Side *e 2 to 7 mm (0.0787 to 0.276 in.) - - - Connect the flow shutting valve (No. 1 water by-pass hose) to the water outlet and slide the clip to secure it.NOTE:
- Make sure to slide the flow shutting valve (No. 1 water by-pass hose until it contacts the hose) stopper of the water outlet.
- Make sure that the tabs of the clip are within the area shown in the illustration.
- Connect the flow shutting valve (No. 1 water by-pass hose) to the water outlet and slide the clip to secure it.
- INSTALL BATTERY CLAMP SUB-ASSEMBLY
Refer to PROCEDURE - Step 42
- INSTALL BATTERY
Refer to INSTALLATION [11/2021 - ]
- INSTALL ECM
Refer to INSTALLATION [11/2021 - ]
- ADD ENGINE COOLANT
Refer to PROCEDURE - Step 5
- INSPECT FOR COOLANT LEAK
Refer to PROCEDURE - Step 1
- INSTALL FRONT FENDER APRON SEAL LH
Refer to PROCEDURE - Step 70
- INSTALL NO. 2 ENGINE UNDER COVER ASSEMBLY
Refer to PROCEDURE - Step 72
- INSTALL NO. 1 ENGINE UNDER COVER
Refer to PROCEDURE - Step 73
- INSTALL FRONT FENDER FRONT SPLASH SHIELD LH
- INSTALL FRONT FENDER FRONT SPLASH SHIELD RH
- INSTALL FRONT WHEEL LH
Refer to INSTALLATION [11/2021 - 03/2023] , or refer to INSTALLATION [03/2023 - 03/2024] , or refer to INSTALLATION [03/2024 - ]