Reassembly [12/2023 - ]: Procedure
- PRECAUTION NOTE:
When installing parts with double-sided tape, heat the portion with adhesive and the application surface of the parts and with a heat light.
Standard Value
Part Temperature Metal parts 40 to 60°C (104 to 140°F) Resin parts 20 to 30°C (68 to 86°F) WARNING:- Do not touch the heat light and heated parts.
- Touching the heat light may result in burns.
- Touching heated parts for a long time may result in burns.
*a Heated Part *b Heat Light NOTE:Do not heat the part excessively.
- INSTALL NO. 2 ROOF DRIP SIDE FINISH MOULDING RETAINER (for Type A)
Torque: 10 N*m (102 kgf*cm, 7 ft.*lbf)
- INSTALL REAR ROOF RACK LEG CUSHION LH (for Type A)
- INSTALL CENTER ROOF RACK LEG CUSHION LH (for Type A)
- INSTALL FRONT ROOF RACK LEG CUSHION LH (for Type A)
- INSTALL FRONT ROOF RACK LEG CUSHION LH (for Type B)
- Clean the roof carrier bar LH surface.
1. Using a heat light, heat the roof carrier bar LH surface.
2. Remove any remaining double-sided tape from the roof carrier bar LH.
3. Wipe off any tape adhesive residue with cleaner.
NOTE:- Installing the front roof rack leg cushion LH with some double-sided tape remaining may cause poor adhesion. Perform this procedure until the tape is sufficiently removed.
- Make sure to use a cloth when removing. Using a screwdriver, etc., may cause damage and poor adhesion.
- Clean the surface even when using a new part.
- Using a heat light, heat the roof carrier bar LH and a new front roof rack leg cushion LH.
- Install the front roof rack leg cushion LH in the position shown in the illustration.
HINT:
Apply pressure so that it does not lift up from the roof carrier bar LH.
- Clean the roof carrier bar LH surface.
- Use the same procedure for the other side.