Installation [12/2021 - ]: Procedure
- INSTALL COMBINATION METER ASSEMBLY
- INSTALL INSTRUMENT CLUSTER FINISH PANEL SUB-ASSEMBLY
- INSTALL LOWER INSTRUMENT PANEL
- INSTALL NO. 1 INSTRUMENT PANEL REGISTER ASSEMBLY
- INSTALL LOWER NO. 1 INSTRUMENT PANEL FINISH PANEL
- INSTALL NO. 2 INSTRUMENT SIDE PANEL
- CUSTOMIZE POWER TILT AND POWER TELESCOPIC STEERING COLUMN SYSTEM
Refer to PROCEDURE - Step 16 - PERFORM REGISTRATION
HINT:
When replacing the combination meter assembly, perform registration.
Refer to REGISTRATION [12/2021 - ]