LEMON Manuals: Even more car manuals for everyone
Home >> Lexus >> 2015 >> IS 250 Base, RWD >> Repair and Diagnosis >> External Pages >> Different car >> Section 5 (Automatic Transmission System (Aa81E) - Service Information (1 Of 2)) >> Shift Lever >> Installation [09/2020 - ] >> Procedure

Installation [09/2020 - ]: Procedure

WARNING: This page does not describe the selected car, but rather 20 other vehicles, including the 2024 Lexus IS 350, 2024 Lexus IS 300, 2023 Lexus IS 350, 2023 Lexus IS 300, and 2022 Lexus IS 350. However, it is still accessible from the selected car via links, so may be relevant.
  1. INSTALL TRANSMISSION FLOOR SHIFT ASSEMBLY 
    1. Temporarily install the transmission floor shift assembly to the vehicle body with the 4 bolts.
      NOTE:

      Do not pinch the wire harness.

      Fig 1: Transmission Floor Shift Assembly Tightening Sequence [09/2020 - ]
      GTY464405Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
    2. Fully tighten the 4 bolts in the order shown in the illustration.

      Torque: 8.3 N*m (85 kgf*cm, 73 in.*lbf) 

    3. Connect the shift lock control ECU connector.
      NOTE:

      Be sure to securely connect the shift lock control ECU connector.

    4. Engage the 4 clamps to the transmission floor shift assembly.
    5. Connect the transmission control switch connector.
      NOTE:

      Be sure to securely connect the transmission control switch connector.

  2. INSTALL NO. 1 CONSOLE BOX DUCT 
    1. Install the No. 1 console box duct with the 2 clips.
    2. Engage the clamp to the No. 1 console box duct.
  3. INSTALL CONSOLE BOX ASSEMBLY 

    Refer to INSTALLATION [09/2020 - 11/2021] , or refer to INSTALLATION [11/2021 - ]

  4. INSTALL FLOOR SHIFT GEAR SHIFTING ROD SUB-ASSEMBLY 
    1. Turn the transmission control shaft lever RH counterclockwise until it stops, then turn it clockwise 2 notches.
      GTY462123Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
      *1 Transmission Control Shaft Lever RH
      *a P
      *b R
      *c N
    2. Move the shift lever to N.
    3. Temporarily install the floor shift gear shifting rod sub-assembly to the lever of the transmission floor shift assembly with the nut.
      GTY465206Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
      *a Lever
      Pushing the lever rearward
    4. Tighten the nut while lightly pushing the lever of the transmission floor shift assembly rearward.

      Torque: 12.8 N*m (131 kgf*cm, 9 ft.*lbf) 

      NOTE:

      Do not push the lever of the transmission floor shift assembly too hard.

  5. INSTALL FRONT NO. 1 FLOOR HEAT INSULATOR 

    Refer to PROCEDURE - Step 5

  6. INSTALL FRONT EXHAUST PIPE ASSEMBLY (for 2GR-FKS) 

    Refer to INSTALLATION [09/2020 - ]

  7. INSTALL FRONT EXHAUST PIPE ASSEMBLY (for 8AR-FTS) 

    Refer to INSTALLATION [09/2020 - ]

  8. INSPECT SHIFT LEVER POSITION 

    See step  1

  9. INSPECT FOR EXHAUST GAS LEAK (for 2GR-FKS) 

    Refer to PROCEDURE - Step 9

  10. INSPECT FOR EXHAUST GAS LEAK (for 8AR-FTS) 

    Refer to PROCEDURE - Step 8