Adjustment [08/2015 - 10/2017]: Procedure

WARNING: This page does not describe the selected car, but rather 20 other vehicles, including the 2024 Lexus IS 350, 2024 Lexus IS 300, 2023 Lexus IS 350, 2023 Lexus IS 300, and 2022 Lexus IS 350. However, it is still accessible from the selected car via links, so may be relevant.
  1. REMOVE FRONT EXHAUST PIPE ASSEMBLY (for 2GR-FSE) 

    Refer to REMOVAL [04/2013 - 10/2016] , or refer to REMOVAL [10/2016 - 10/2017]

  2. REMOVE FRONT EXHAUST PIPE ASSEMBLY (for 8AR-FTS) 

    Refer to REMOVAL [08/2015 - 10/2016] , or refer to REMOVAL [10/2016 - 09/2020]

  3. REMOVE FRONT NO. 1 FLOOR HEAT INSULATOR 

    Refer to PROCEDURE - Step 3

  4. ADJUST SHIFT LEVER POSITION 
    1. Move the shift lever to N.
    2. Remove the nut and separate the floor shift gear shifting rod sub-assembly from the lever of the transmission floor shift assembly.
      GTY462357Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
      *a Lever
    3. Turn the transmission control shaft lever RH counterclockwise until it stops, then turn it clockwise 2 notches.
      GTY462123Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
      *1 Transmission Control Shaft Lever RH
      *a P
      *b R
      *c N
    4. Temporarily install the floor shift gear shifting rod sub-assembly to the lever of the transmission floor shift assembly with the nut.
      GTY465206Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
      *a Lever
      Pushing the lever rearward
    5. Tighten the nut while lightly pushing the lever of the transmission floor shift assembly rearward.

      Torque: 12.8 N*m (131 kgf*cm, 9 ft.*lbf) 

      NOTE:

      Do not push the lever of the transmission floor shift assembly too hard.

  5. INSTALL FRONT NO. 1 FLOOR HEAT INSULATOR 

    Refer to PROCEDURE - Step 5

  6. INSTALL FRONT EXHAUST PIPE ASSEMBLY (for 2GR-FSE) 

    Refer to INSTALLATION [04/2013 - 10/2016] , or refer to INSTALLATION [10/2016 - 10/2017]

  7. INSTALL FRONT EXHAUST PIPE ASSEMBLY (for 8AR-FTS) 

    Refer to INSTALLATION [08/2015 - 10/2016] , or refer to INSTALLATION [10/2016 - 09/2020]

  8. INSPECT SHIFT LEVER POSITION 

    See step  1

  9. INSPECT FOR EXHAUST GAS LEAK (for 2GR-FSE) 

    Refer to PROCEDURE - Step 9 [04/2013 - 10/2016] , or refer to PROCEDURE - Step 9 [10/2016 - 10/2017]

  10. INSPECT FOR EXHAUST GAS LEAK (for 8AR-FTS) 

    Refer to PROCEDURE - Step 8 [08/2015 - 10/2016] , or refer to PROCEDURE - Step 8 [10/2016 - 09/2020]