Installation [04/2013 - 10/2016]: Procedure

  1. INSTALL COMBINATION METER ASSEMBLY 
    1. Connect each connector.
    2. Engage the clamp.
    3. Install the combination meter assembly with the 4 screws.
  2. INSTALL METER HOOD SUB-ASSEMBLY 

    Refer to PROCEDURE - Step 31

  3. INSTALL LOWER INSTRUMENT PANEL FINISH PANEL SUB-ASSEMBLY 

    Refer to PROCEDURE - Step 34

  4. CONNECT HOOD LOCK CONTROL LEVER SUB-ASSEMBLY 

    Refer to PROCEDURE - Step 35

  5. INSTALL NO. 1 INSTRUMENT PANEL UNDER COVER SUB-ASSEMBLY 

    Refer to PROCEDURE - Step 36

  6. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL 
    NOTE:

    When disconnecting the cable, some systems need to be initialized after the cable is reconnected.

    Refer to INITIALIZATION [04/2013 - 06/2014] , or refer to INITIALIZATION [06/2014 - 08/2015] , or refer to INITIALIZATION [08/2015 - 10/2016]

  7. CUSTOMIZE POWER TILT AND POWER TELESCOPIC STEERING COLUMN SYSTEM (for Power Tilt and Power Telescopic Steering Column) 

    Refer to PROCEDURE - Step 19 [04/2013 - 06/2014] , or refer to PROCEDURE - Step 19 [06/2014 - 08/2015] , or refer to PROCEDURE - Step 19 [08/2015 - 10/2016]