Installation [04/2013 - 10/2017]: Procedure
- INSTALL V-RIBBED BELT
- Set the V-ribbed belt onto every pulley.
*1 Water Pump Assembly *2 Generator Assembly *3 No. 2 Idler Pulley Sub-assembly *4 V-ribbed Belt Tensioner Assembly *5 Crankshaft Pulley *6 Compressor and Magnetic Clutch Assembly NOTE:- Put the backside of the V-ribbed belt on the V-ribbed belt tensioner pulley and No. 2 idler pulley sub-assembly.
- Check that the V-ribbed belt is properly set to each pulley.
- While turning the V-ribbed belt tensioner assembly counterclockwise, remove the bar.
- If it is difficult to install the V-ribbed belt, perform the following procedure.
- Check that the V-ribbed belt fits properly in the ribbed grooves.
HINT:
Make sure to check by hand that the V-ribbed belt has not slipped out of the grooves on the bottom of the crankshaft pulley.
- Set the V-ribbed belt onto every pulley.
- INSTALL V-BANK COVER SUB-ASSEMBLY
Refer to PROCEDURE - Step 105 [04/2013 - 08/2015] , or refer to PROCEDURE - Step 106 [08/2015 - 10/2016] , or refer to PROCEDURE - Step 106 [10/2016 - 10/2017]
- INSTALL INLET NO. 1 AIR CLEANER
Refer to PROCEDURE - Step 75 [04/2013 - 08/2015] , or refer to PROCEDURE - Step 76 [08/2015 - 10/2016] , or refer to PROCEDURE - Step 77 [10/2016 - 10/2017]
- INSTALL COOL AIR INTAKE DUCT SEAL
Refer to PROCEDURE - Step 3 [04/2013 - 10/2016] , or refer to PROCEDURE - Step 2 [10/2016 - 09/2020]