Installation [09/2012 - ]
- INSTALL COMBINATION METER ASSEMBLY
- Connect the connector and attach the 2 claws to close the connector cover.
- Install the combination meter assembly with the 4 screws.
- INSTALL STEERING COLUMN COVER (w/o Driver Monitor Camera) . Refer to INSTALLATION [09/2012 - ] - Step 9
- INSTALL STEERING COLUMN COVER (w/ Driver Monitor Camera) . Refer to INSTALLATION [09/2012 - ] - Step 10
- INSTALL NO. 2 INSTRUMENT CLUSTER FINISH PANEL SUB-ASSEMBLY
- Connect the 2 connectors.
- Attach the 6 clips to install the No. 2 instrument cluster finish panel sub-assembly.
- Install the 2 clips.
- INSTALL NO. 1 INSTRUMENT PANEL SAFETY PAD SUB-ASSEMBLY . Refer to INSTALLATION [09/2012 - ] - Step 28
- INSTALL INSTRUMENT PANEL ORNAMENT . Refer to INSTALLATION [09/2012 - ] - Step 29
- INSTALL INSTRUMENT SIDE PANEL LH . Refer to INSTALLATION [09/2012 - ] - Step 30
- CONNECT CABLE TO NEGATIVE BATTERY TERMINAL NOTE:
When disconnecting the cable, some systems need to be initialized after the cable is reconnected. Refer to INITIALIZATION [09/2012 - ] .
- ENABLE AUTOAWAY/RETURN FUNCTION
- Restore the autoaway/return function setting to the previous condition by changing the customize parameter. Refer to CUSTOMIZE PARAMETERS [09/2012 - ] .
- INSTALL COWL TOP VENTILATOR LOUVER RH . Refer to INSTALLATION [09/2012 - ] - Step 15