Home >> Land Rover >> 2022 >> Defender 90 S >> Repair and Diagnosis >> External Pages >> Different variant/trim >> Section 26 (Fuel Charging And Controls - V8 S/C 5.0L Petrol -- Defender/L663) >> Fuel Charging And Controls - V8 S/C 5.0L Petrol (G2796609) >> Description And Operation >> Fuel Charging And Controls - V8 S/C 5.0L Petrol (G2796610) >> Description >> High Pressure Fuel Pump

High Pressure Fuel Pump

WARNING: This page is about a different variant/trim than selected.
G11688927Courtesy of JAGUAR LAND ROVER NORTH AMERICA, LLC
ITEM DESCRIPTION
1 Crankshaft
2 Auxiliary drive chain
3 Auxiliary camshaft
4 Tappet
5 HP  fuel pump
6 Acoustic cover

The 2 HP  fuel pumps are identical mechanically-driven pumps installed on the right side of the oil pan, behind the generator. An O-ring seals each of the HP  fuel pumps in the oil pan. The front HP  fuel pump is identified as No. 1 pump, the rear HP  fuel pump is identified as No. 2 pump. An acoustic cover is installed on each of the HP  fuel pumps.

The HP  fuel pumps are single-plunger pumps. The plunger of each pump extends through the oil pan and the carrier of the auxiliary camshaft. A tappet on the end of each plunger is operated by a 2-lobe cam on the auxiliary camshaft. A spring installed on the outside of the plunger ensures the plunger and tappet remain in contact with the cam.

The auxiliary camshaft is driven by the crankshaft, through the auxiliary drive chain, at engine speed. The auxiliary camshaft is timed to match the pump delivery strokes with crankshaft position.

High Pressure Fuel Pump Schematic 

G11588306Courtesy of JAGUAR LAND ROVER NORTH AMERICA, LLC
ITEM DESCRIPTION
1 Pressure Relief Valve (PRV)
2 To HP  fuel lines
3 Outlet check valve
4 Plunger
5 Feed connection from LP  fuel lines
6 Damper chamber
7 Fuel metering valve

In addition to the plunger, each HP  fuel pump contains:

The fuel metering valve regulates the output pressure from the HP  fuel pump. The fuel metering valve is a normally open solenoid valve controlled by the PCM  . During the inlet stroke of the plunger the fuel metering valve is de-energized, which allows LP  fuel into the pumping chamber. The PCM  energizes the fuel metering valve closed during the delivery stroke of the plunger, which forces the fuel in the pumping chamber through the check valve into the HP  lines. By changing the closing point of the fuel metering valve, the PCM  can determine the volume of fuel output during the delivery stroke, and thus the pressure in the HP  side of the system.

The check valve prevents the return of HP  fuel to the pumping chamber during the inlet stroke of the plunger.

The PRV protects the HP  side of the system from excessive pressure if there is a failure of the fuel metering valve. If the pump delivery pressure increases to 250 bar (3625 lbf/in2 ), the PRV opens and returns fuel to the inlet side of the plunger.