  1. Clean all gasket surfaces.
  2. Replace intake manifold gasket seals.
  3. Position the foam pad over the coolant transfer tube.
  4. Position the manifold onto the two studs.
  5. Install the intake manifold and tighten the fasteners (1 & 2) to 12 N.m (9 ft. lbs.).
    GC0156110Courtesy of CHRYSLER GROUP, LLC
  6. Connect the vacuum hoses at the intake manifold (3).
    GC0155794Courtesy of CHRYSLER GROUP, LLC
  7. Install the intake manifold silencer cover and screws (1). Tighten the screws (1) to 2.5 N.m (22 in. lbs.).
    GC0156429Courtesy of CHRYSLER GROUP, LLC
  8. Connect and lock the four VVAA solenoid wire harness connectors.
  9. Connect and lock the fuel injector wire harness connectors (1).
    GC0169971Courtesy of CHRYSLER GROUP, LLC
  10. Install the injector silencer pad (3) over the fuel rail.
  11. Connect fuel line (1) to the fuel rail. Refer to STANDARD PROCEDURE .
  12. Connect the purge vapor line (2).
  13. Engage intake manifold wire harness retainers.
    GC0160072Courtesy of CHRYSLER GROUP, LLC
  14. Move the right side of the engine rearward back into its proper position. Make sure the mount is not against the frame while being moved. 
  15. Install the two right engine mount to frame rail bolts (2).
  16. Install the right engine mount to strut tower bolt (4).
  17. Tighten the right engine mount to strut tower bolt to 65 N.m (48 ft. lbs.).
  18. Tighten the two right engine mount to frame rail bolts to 105 N.m (77 ft. lbs.).
    GC0159480Courtesy of CHRYSLER GROUP, LLC
  19. Install the pressurized coolant bottle (3). Tighten the bolts (4) to 8 N.m (70 in. lbs.).
    GC0159988Courtesy of CHRYSLER GROUP, LLC
  20. Install the air cleaner body bracket (1) with two nuts (2).
  21. Tighten the nuts (2) to 8 N.m (70 in. lbs.).
    GC0155543Courtesy of CHRYSLER GROUP, LLC
  22. Install the throttle body (3) to the intake manifold.
  23. Install the three throttle body screws (1) and one throttle body bolt (2). Tighten all to 8 N.m (71 in. lbs.).
    GC0155590Courtesy of CHRYSLER GROUP, LLC
  24. Install the throttle body support bracket (2). Tighten the fasteners (1 and 3) to 8 N.m (71 in. lbs.).
    GC0156353Courtesy of CHRYSLER GROUP, LLC
  25. Install the intake manifold support bracket (3). Install the two nuts (1) and one bolt (2). Tighten to 9 N.m (80 in. lbs.).
    GC0159295Courtesy of CHRYSLER GROUP, LLC
  26. Raise and support the vehicle. Refer to HOISTING, STANDARD PROCEDURE .
  27. Install a new gasket (5) and loosely install the cross-under pipe to catalytic converter outlet flange nuts (4).
  28. Loosely install the cross-under pipe support bolt (3).
  29. Tighten the cross-under pipe flange nuts to 19 N.m (14 ft. lbs.).
  30. Tighten the cross-under pipe support bolt to 25 N.m (18 ft. lbs.).
  31. Install the belly pan, if removed.
  32. Install the front and rear skid plates, if removed.
    GC0156110Courtesy of CHRYSLER GROUP, LLC
  33. Connect and lock the MAP sensor wire harness connector (2).
  34. Engage the wire harness to the manifold eyelets (1).
  35. Install the air cleaner resonator. .
  36. Install the air cleaner body. Refer to INSTALLATION  .
  37. Install the cowl plenum panel and cowl plenum extension. Refer to COVER, COWL PANEL, INSTALLATION .
  38. Connect the negative battery cable. If equipped with an Intelligent Battery Sensor (IBS), connect the IBS connector.
    GC0159679Courtesy of CHRYSLER GROUP, LLC
  39. Install the engine cover (1) to the ball studs (2).