Manifold, Intake: Installation: Lower

Fig 1: Lower Intake Manifold To Cylinder Head Seals
GC0144265Courtesy of CHRYSLER GROUP, LLC
  1. Clean and inspect the sealing surfaces. Install new lower intake manifold to cylinder head seals (1).
    Fig 2: Identifying Fuel Rail Bolt Tightening Sequence
    GC0147420Courtesy of CHRYSLER GROUP, LLC
  2. If removed, install the fuel injectors and the fuel rail (1) to the lower intake manifold. Tighten the four bolts in the sequence shown in illustration to 7 N.m (62 in. lbs.). Refer to RAIL, FUEL, INSTALLATION .
    Fig 3: Lower Intake Manifold Tightening Sequence
    GC0147424Courtesy of CHRYSLER GROUP, LLC
  3. Position the lower intake manifold (1) on the cylinder head surfaces.
  4. Install the manifold attaching bolts and tighten in the sequence shown in illustration to 12 N.m (106 in. lbs.).
    Fig 4: Injection/Ignition Harness Retainer & Main Wire Harness Retainer
    GC0144480Courtesy of CHRYSLER GROUP, LLC
  5. Engage the main wire harness retainer (2) to the rear of the lower intake manifold.
  6. Engage the injection/ignition harness retainer (1) to the rear of the lower intake manifold.
    Fig 5: Fuel Supply Line And Connectors
    GC0147423Courtesy of CHRYSLER GROUP, LLC
  7. Connect the fuel injector electrical connectors (1).
  8. Connect the fuel supply hose (2) to the fuel rail. Refer to FITTING, QUICK CONNECT .
    Fig 6: Intake Ports, Insulator & Alignment Posts
    GC0144184Courtesy of CHRYSLER GROUP, LLC
  9. Install the insulator (2) to the two alignment posts (3) on top of the LH cylinder head cover.
    Fig 7: Upper Intake Manifold Tightening Sequence
    GC0154022Courtesy of CHRYSLER GROUP, LLC
  10. Install the upper intake manifold (1), support brackets and air cleaner body. Refer to MANIFOLD, INTAKE, INSTALLATION .
  11. Connect the negative battery cable and tighten nut to 5 N.m (45 in. lbs.).
  12. Start the engine and check for leaks.