Rear SUBFRAME - Project 8 (G2248720): Installation
- Install the differential and 2 bolts.
Renew Part: Differential case rear bolts Quantity: 2 .
Torque : 192Nm
- Install the 2 differential mounting bolts.
Renew Part: Differential case front bolt(s) Quantity: 2 .
Torque : 110Nm
- Install the suspension arms to the rear subframe.
Renew Part: Rear lower arm to subframe nut and bolt Quantity: 4 .
Torque
Stage 1: 70Nm
Stage 2: 240°
- Install the 2 halfshafts to the differential.
- Install the 2 upper control arm to subframe nuts and bolts.
Renew Part: Upper control arm nuts and bolts Quantity: 2 .
Torque
Stage 1: 60Nm
Stage 2: 60°
- Install the tie-rods to the rear subframe.
Renew Part: Toe arm nut(s) Quantity: 2 .
Torque
Stage 1: 60Nm
Stage 2: 90°
-
NOTE: Repeat the step for the other side.
Install the 2 bolts and height sensor assembly.
Torque : 7Nm
-
- Install the 4 bolts and stabilizer bar.
Renew Part: Rear stabilizer bar to subframe bolts Quantity: 4 .
Torque : 60Nm
- Install the 2 upper stabilizer bar link retaining nuts.
Renew Part: Stabilizer bar link retaining nut(s) Quantity: 2 .
Torque : 60Nm
- Install the 4 bolts and stabilizer bar.
-
- Connect the 4 wiring harness electrical connectors.
- Secure the 8 grommets and 23 retaining clips.
- Install the rear springs to the subframe.
-
WARNING: Make sure the rear subframe is supported using a suitable stand and retaining straps.
Using a suitable stand install the 4 bolts and subframe assembly.
Renew Part: Rear subframe to body bolts Quantity: 4 .
Torque
Stage 1: 110Nm
Stage 2: 180°
- Install the 8 subframe to body mounting bolts.
Torque : 60Nm
- Align the driveshaft and install the 6 bolts to the driveshaft and differential input flange.
Renew Part: Driveshaft flange bolts Quantity: 6 .
Torque : 48Nm
- Connect the fuel filler pipe to the fuel tank.
- Install the 2 bolts and heatshield.
Torque : 24Nm
- Install the shock absorber lower nuts and bolts.
Renew Part: Shock absorber nut and bolt Quantity: 2 .
Torque
Stage 1: 70Nm
Stage 2: 120°
- Connect the electrical connector and secure the retaining clip.
-
- Connect the 2 rear differential oil cooler hoses.
Torque : 30Nm
- Install the mounting the nut and bolt.
Torque : 10Nm
- Connect the 2 rear differential oil cooler hoses.
- Fill the differential.
Refer to: DIFFERENTIAL DRAINING AND FILLING VEHICLES WITH HEAVY DUTY DIFFERENTIAL
- Install the rear right wheel arch liner.
Refer to: REAR WHEEL ARCH LINER - PROJECT 8
- Install the front silencer.
Refer to: FRONT SILENCER
- Install the rear brake pads.
Refer to: BRAKE PADS
- Connect the startup battery ground cable.
Refer to: STARTUP BATTERY DISCONNECT AND CONNECT
- Using only four-wheel alignment equipment approved by Jaguar Land Rover, check and adjust the wheel alignment.
Refer to: FOUR WHEEL ALIGNMENT - PROJECT 8
General Equipment: Four wheel alignment equipment