Battery Charging
It is essential that a suitably ventilated defined area exists in each retailer for battery charging.
Batteries MUST BE tested and if necessary charged every 30 days and charged after 90 days irrespective of any test. It is recommended that retailers always have fully charged batteries ready for use.
A designated controlled area must be allocated for scrap batteries and clearly controlled as such.
To bring a discharged but serviceable battery back to a fully charged condition proceed as follows:
- Check and if necessary top-up the battery electrolyte level. (Flooded maintainable batteries only)
- Charge the battery using a JLR approved charger as detailed in the approved equipment document following the manufacturers operating instructions.
Following charging, a post charge battery condition test must be carried out in accordance with the table shown in the Determining Battery Condition section (Section 6) of this procedure .
Any actions must be carried out in accordance with the table shown in the Determining Battery Condition section (Section 6) of this procedure . The details must be recorded on the New Vehicle Storage Form which is part of the new vehicle storage document.
For additional information, refer to: New Vehicle Storage Form (Vehicle Transportation Aids and Vehicle Storage, Description and Operation).