Circuit/System Testing
- Ignition OFF, disconnect the harness connector at the DIC switch assembly.
- Verify all of the scan tool DIC Switch parameters are Inactive.
- If not Inactive, test both signal circuits terminal 1 and terminal 3 for a short to ground. If the circuits test normal, replace the IPC.
- Ignition ON, install a 3-amp fused jumper wire between both signal circuits terminal 1, terminal 3, and ground. Verify all of the scan tool DIC Switch parameters are Active.
- If not Active, test both signal circuits of the DIC switch assembly for a short to voltage. If the circuits test normal, replace the IPC.
- If all circuits test normal, test or replace the DIC switch assembly.