Circuit/System Testing

WARNING: This page is about a different variant/trim than selected.
  1. Ignition OFF, disconnect the X176 24-way harness connector at the transmission, then the X1 16-way harness connector at the transmission, verify that a test lamp does not illuminate between the ignition voltage circuit terminal 12 and ground.
    • If the test lamp illuminates, test the ignition voltage circuit for a short to voltage.
  2. Ignition ON, verify that a test lamp illuminates between the ignition voltage circuit terminal 12 and ground.
    • If the test lamp does not illuminate, test the ignition voltage circuit for a short to ground or an open/high resistance.
    • If the circuit tests normal replace the Q8 control solenoid valve assembly.