Circuit/System Testing
WARNING: This page is about a different car, the 2010 GMC Sierra, 2010 GMC Cab & Chassis Sierra, 2010 Chevrolet Silverado, and 2010 Chevrolet Cab & Chassis Silverado. However, it is still accessible from the selected car via links, so may be relevant.
- Ignition OFF, remove the Q8 control solenoid valve assembly. Refer to Control Solenoid Valve and Transmission Control Module Assembly Replacement .
- Connect the DT-47825-10: jumper harness between the vehicle wire harness electrical connector, and the Q8 control solenoid valve assembly electrical connector.
- Ignition ON, test for 8.3-9.3 volts between the ISS/OSS voltage circuit terminal B on the Q8 control solenoid valve assembly and ground at the transmission case.
- If not within the specified range, replace the control solenoid valve assembly.
- Perform the Control Solenoid Valve and Transmission Control Module Assembly Input Shaft Speed/Output Shaft Speed Input Test .
- Inspect the machined teeth on the 1-2-3-4 and 3-5 clutch housing outer surface for damage or misalignment. Repair or replace as necessary.
- If all of the above test normal, replace the B14A/B14C ISS/OSS assembly.
NOTE:
You must perform the Circuit/System Verification first.