Oil Pan: Installation
WARNING: This page is about a different car, the 2013 Ford Explorer. However, it is still accessible from the selected car via links, so may be relevant.
- Apply a 5.5 mm (0.21 in) bead of Motorcraft® High Performance Engine RTV Silicone to the 2 engine front cover-to-cylinder block joint areas on the sealing surface of the oil pan.
-
NOTE: Failure to use Motorcraft® High Performance Engine RTV Silicone may cause the engine oil to foam excessively and result in serious engine damage.NOTE: The oil pan and the 4 specified bolts must be installed and the oil pan aligned to the cylinder block within 4 minutes of sealant application. Final tightening of the oil pan bolts must be carried out within 60 minutes of sealant application.
Apply a 3 mm (0.11 in) bead of Motorcraft® High Performance Engine RTV Silicone to the sealing surface of the oil pan-to-engine block and to the oil pan-to-engine front cover mating surface.
- Apply a 5.5 mm (0.21 in) bead of Motorcraft® High Performance Engine RTV Silicone to the 2 crankshaft seal retainer plate-to-cylinder block joint areas on the sealing surface of the oil pan.
-
NOTE: The oil pan and the 4 specified bolts must be installed within 4 minutes of the start of sealant application.NOTE: Keep the oil pan as close as possible to the transmission while installing, then slide forward towards the engine front cover to prevent wiping off of the sealant.
Install the oil pan and bolts 10, 11, 13 and 14 finger tight.
- Draw the bellhousing up to the engine by tightening the LH bellhousing-to-engine bolt.
- Draw the bellhousing up to the engine by tightening the RH engine-to-bellhousing bolt.
- Install the 4 oil pan-to-bellhousing bolts.
- Install the A/C compressor stud and nut.
- Tighten bolts 10, 11, 13 and 14 in the sequence shown in illustration to 3 Nm (27 lb-in).
- Install the 4 lower engine front cover bolts.
- Install the remaining oil pan bolts and tighten in the sequence shown in illustration.
- Tighten the 4 lower engine front cover bolts to 24 Nm (18 lb-ft).
- Tighten the A/C
compressor nut to 25 Nm (18 lb-ft).
- Attach the wiring harness retainer to the A/C compressor stud.
- Tighten the 4 oil pan-to-bellhousing bolts to 48 Nm (35 lb-ft).
- Tighten the RH engine-to-bellhousing bolt to 48 Nm (35 lb-ft).
- Tighten the 3 LH bellhousing-to-engine bolts to 48 Nm (35 lb-ft).
- Install the inspection cover and the 2 fasteners.
- Install the Power Transfer Unit (PTU) support bracket and the 3 bolts.
-
NOTE: Lubricate the O-ring seals with clean engine oil.
Install 2 new O-ring seals and new gasket on the oil return tube.
-
NOTE: Lubricate the oil pan bore with clean engine oil.
Install the LH turbocharger oil return tube in the oil pan and install the 2 bolts.
- Tighten the 3 upper bellhousing-to-engine bolts to 48 Nm (35 lb-ft).
- Install the RH turbocharger bracket and the 3 bolts.
- Install the intermediate shaft assembly. REFER to INTERMEDIATE SHAFT -- 3.5L GTDI .
-
NOTE: Do not lubricate the engine oil filter gasket.
Install a new engine oil filter.
- Install the 2 engine roll restrictors. REFER to TRANSMISSION SUPPORT INSULATOR - ANTI-ROLL FWD , or TRANSMISSION SUPPORT INSULATOR - ANTI-ROLL AWD .
- Install the RH and LH catalytic converters. Refer to CATALYTIC CONVERTER -- LH, 3.5L GTDI , and CATALYTIC CONVERTER -- RH, 3.5L GTDI .
- Install the underbody air duct and the 3 twist lock retainers.
- Install the starter stud bolt.
- Install the oil level indicator.
- Install the battery tray. REFER to BATTERY AND BATTERY TRAY - EXPLODED VIEW .
- Install the ACL outlet pipe. REFER to INTAKE AIR SYSTEM COMPONENTS - EXPLODED VIEW .
-
NOTE: Do not expose the Motorcraft® High Performance Engine RTV Silicone to engine oil for at least 90 minutes after installing the oil pan. Failure to follow these instructions may cause engine oil leakage.
Fill the engine with clean engine oil.