Removal and Installation
- Remove the battery tray. For additional information, refer to BATTERY TRAY .
- Remove the bolt and position the battery cable body ground terminal aside.
- To install, tighten to 12 Nm (106 lb-in).
- Remove the nut and position the Battery Junction Box (BJB) cable terminal aside.
- To install, tighten to 12 Nm (106 lb-in).
- Remove the starter solenoid terminal cover.
- Remove the starter solenoid terminal nut and position the battery cable starter solenoid terminal aside.
- To install, tighten to 6 Nm (53 lb-in).
- Remove the starter B+ nut and position the battery cable starter motor terminal aside.
- To install, tighten to 12 Nm (106 lb-in).
- Release the battery cable locator from the engine.
- Remove the bolt and position the battery cable engine ground terminal aside.
- To install, tighten to 12 Nm (106 lb-in).
- Release the battery cable from the top of the intake manifold.
- Release the 3 battery cable locators from the LH valve cover.
- Position the generator protective cover aside, remove the nut and position the generator B+ terminal aside.
- To install, tighten to 17 Nm (150 lb-in).
- Remove the battery cables.
- To install, reverse the removal procedure.