Insulator, Engine Mount, Left: Installation

WARNING: This page is about a different variant/trim than selected.
GC0152988Courtesy of CHRYSLER GROUP, LLC
  1. If removed, install the left engine mount bracket to the manual transmission with three bolts (1) tightened to 50 N.m (37 ft. lbs.).
    GC0152660Courtesy of CHRYSLER GROUP, LLC
  2. If removed, install the left engine mount bracket (1) to the automatic transmission with three bolts (2) tightened to 60 N.m (44 ft. lbs.).
    GC0152421Courtesy of CHRYSLER GROUP, LLC
    NOTE:

    Automatic transmission equipped engine mount shown, manual transmission equipped engine mount similar.

  3. Install the LH engine mount isolator (1) with three bolts (2 and 3). First tighten the isolator to engine bracket bolt (3) to 110 N.m (81 ft. lbs.) and then tighten the isolator to body bolts (2) to 50 N.m (37 ft. lbs.).
    GC0152449Courtesy of CHRYSLER GROUP, LLC
  4. Raise and support the vehicle. Refer to HOISTING .
  5. Install the tunnel support brace (2) with four bolts (1) tightened to 90 N.m (60 ft. lb.).
    GC0082359Courtesy of CHRYSLER GROUP, LLC
  6. Install the belly pan. Refer to BELLY PAN, INSTALLATION .
    GC0152394Courtesy of CHRYSLER GROUP, LLC
  7. Position the battery tray and PCM in the vehicle. Route the wire harness and close the wire harness retainers (3).
  8. Install the ground strap (4) with nut (1) tightened to 5 N.m (44 in. lbs.).
    GC0152563Courtesy of CHRYSLER GROUP, LLC
  9. Install the battery tray (3) with one nut (5) and two bolts (1) tightened to 25 N.m (18 ft. lbs.).
  10. Engage the engine wire harness connector (2) to the battery tray (3).
  11. Engage two engine wire harness retainers (4) to the battery tray (3).
  12. Engage two starter wire harness retainers (6) to the battery tray (3).
    GC0152393Courtesy of CHRYSLER GROUP, LLC
  13. Connect the Powertrain Control Module (PCM) harness connectors (1 and 2).
    GC0153787Courtesy of CHRYSLER GROUP, LLC
  14. Install and connect the battery. Refer to BATTERY, INSTALLATION .
  15. Install the air cleaner body (1). Refer to BODY, AIR CLEANER, INSTALLATION .