LEMON Manuals: Even more car manuals for everyone
Home >> Chrysler >> 2011 >> 300 C, RWD >> Repair and Diagnosis >> External Pages >> Different car >> Section 443 (Base Brakes (Service Information)) >> Hydraulic/Mechanical >> Booster, Power Brake >> Installation >> Right-Hand-Drive - 3.6L Gas Engine

Right-Hand-Drive - 3.6L Gas Engine

WARNING: This page is about a different car, the 2013 Dodge Avenger and 2013 Chrysler 200. However, it is still accessible from the selected car via links, so may be relevant.
Fig 1: Booster Seal
GC0082140Courtesy of CHRYSLER GROUP, LLC
NOTE:

Before power brake booster (1) installation, be certain a NEW dash seal (2) is installed on the booster mounting studs.

Fig 2: Pedal And Booster Mounting - RHD
GC0098417Courtesy of CHRYSLER GROUP, LLC
  1. Install the power brake booster (1) into the engine compartment over the top center of the engine. Rotate the booster using the reverse version of how it was removed. Slide the power brake booster push rod and studs through the dash panel and into mounting position.
    Fig 3: Jack Supporting Oil Pan
    GC0120816Courtesy of CHRYSLER GROUP, LLC
  2. Slowly raise the right side of the engine using the floor jack (3), to a point where the right engine mount bracket can be easily installed.
    Fig 4: Identifying Right Engine Mount Bracket
    GC0120817Courtesy of CHRYSLER GROUP, LLC
  3. Position the right engine mount bracket and install the two nuts (1) and three bolts (2). Refer to INSULATOR, ENGINE MOUNT, LEFT, INSTALLATIONINSULATOR, ENGINE MOUNT, REAR, INSTALLATION or INSULATOR, ENGINE MOUNT, RIGHT, INSTALLATION .
  4. Remove the floor jack and block of wood from below engine.
    Fig 5: Pedal And Booster Mounting - RHD
    GC0098417Courtesy of CHRYSLER GROUP, LLC
  5. Under the instrument panel, install the four power brake booster mounting nuts (4). To tighten the nuts, refer to the following step:
    Fig 6: Mounting Nut Torque Sequence - RHD
    GC0082344Courtesy of CHRYSLER GROUP, LLC
    CAUTION:

    Because of power brake booster design, it is very important to tighten the mounting nuts in the proper sequence as shown in illustration.

  6. Tighten the four brake pedal/booster mounting nuts in the proper sequence to 23 N.m (17 ft. lbs.).
    Fig 7: Brake Pedal Clip - RHD
    GC0082338Courtesy of CHRYSLER GROUP, LLC
  7. Using Mopar® Lubriplate, or an equivalent, coat the surface of the brake pedal pin (3) where it contacts the brake booster input rod (2).
  8. Install the power brake booster push rod (2) on the pin (3) mounted on the side of the brake pedal. Install a NEW retaining clip (1) on the end of the pin. Do not reuse the old clip. 
  9. Reinstall and adjust the stop lamp switch that was set aside for reuse. Refer to SWITCH, STOP LAMP, INSTALLATION .
  10. Install the steering column opening cover on the instrument panel. Refer to COVER, STEERING COLUMN OPENING, INSTALLATION .
  11. Install the brake tube routing clips with tubes onto the studs on the dash panel.
    Fig 8: Vacuum Hose At Booster - RHD
    GC0120815Courtesy of CHRYSLER GROUP, LLC
  12. Connect the vacuum hose (2) to the check valve (1) on the power brake booster.
  13. Install the master cylinder. Refer to MASTER CYLINDER, BRAKE, INSTALLATION .
    Fig 9: Vacuum Hose At Booster - RHD
    GC0120815Courtesy of CHRYSLER GROUP, LLC
  14. Install the booster vacuum hose routing clip (4) onto the master cylinder mounting stud.
  15. Install the vacuum hose routing clip (3) onto the stud on the dash panel.
    Fig 10: A/C Liquid And Suction Line Assembly
    GC0083944Courtesy of CHRYSLER GROUP, LLC
  16. Remove the tape or plugs from the refrigerant line fittings and the evaporator ports.
  17. Lubricate the rubber O-rings on new dual-plan seals with clean refrigerant oil and install the seals onto the liquid and suction line fittings. Use only the specified seals as they are made of special materials compatible to the R-134a system. Use only refrigerant oil of the type recommended for the air conditioning compressor in the vehicle.
  18. Connect the air conditioning liquid and suction line assembly to the air conditioning evaporator (6).
  19. Install the bolt (3) that secures the air conditioning liquid and suction line assembly to the air conditioning evaporator. Tighten the bolt to 12 N.m (105 in. lbs.).
  20. Install the nut (1) that secures the air conditioning line bracket (2) to the right front strut tower (5). Tighten the nut to 4.5 N.m (40 in. lbs.).
  21. Install the power steering fluid reservoir. Refer to RESERVOIR, POWER STEERING PUMP, INSTALLATION .
  22. Install the coolant recovery bottle. Refer to BOTTLE, COOLANT RECOVERY, INSTALLATION .
    Fig 11: Heat Shield
    GC0083943Courtesy of CHRYSLER GROUP, LLC
  23. Position the heat shield (3) onto the studs (2) located on the dash panel in the engine compartment.
  24. Install the upper fastener (1) securing the heat shield to the dash panel. Tighten all three fasteners to 1 N.m (10 in. lbs.).
  25. Install the rear cylinder head cover . Refer to 2.4L COVER(S), CYLINDER HEAD, INSTALLATION or 3.6L COVER(S), CYLINDER HEAD, INSTALLATION .
  26. Install the engine upper intake manifold. Refer to 2.4L MANIFOLD, INTAKE, INSTALLATION or 3.6L MANIFOLD, INTAKE, INSTALLATION .
  27. Install the engine appearance cover.
  28. Connect the battery negative (ground) cable to its post on the battery.
  29. Bleed the base brake system as necessary. Refer to STANDARD PROCEDURE - BASE BRAKE BLEEDING  .
  30. Using a refrigerant recovery machine, evacuate and charge the refrigerant system. Refer to PLUMBING, STANDARD PROCEDURE .
    WARNING:

    Be certain a firm brake pedal is achieved prior to attempting to operate the vehicle.

  31. Road test the vehicle to ensure proper operation of the brakes.