Diagnostic Test
WARNING: This page is about a different car, the 2015 RAM 3500 HD and 2015 RAM 2500 HD. However, it is still accessible from the selected car via links, so may be relevant.
- ACTIVE DTC NOTE:
If there are any 5-Volt supply DTCs present, repair those DTCs before proceeding.
- Turn the ignition on.
- With the scan tool, record all Freeze frame data.
- With the scan tool, erase DTCs.
- Turn the ignition off for 75 seconds.
- Start, or attempt to start the engine.
- With the scan tool, read DTCs.
Did the DTC reset?
Yes
- Go To 2
No
- Perform the INTERMITTENT CONDITION diagnostic procedure. Refer to INTERMITTENT CONDITION - 6.7L .
- CHECK THE (K24) SIGNAL CIRCUIT FOR AN OPEN/HIGH RESISTANCE
- Turn the ignition off.
- Disconnect the PCM C1 harness connector.
- Disconnect the CKP Sensor harness connector.NOTE:
Check connectors - Clean/repair as necessary.
- Measure the resistance of the (K24) CKP Signal circuit between the PCM C1 harness connector and the CKP Sensor harness connector.
Is the resistance below 5.0 Ohms?
Yes
- Go To 3
No
- Repair the (K24) CKP Signal circuit for an open or high resistance.
- Perform the POWERTRAIN VERIFICATION TEST - 6.7L. Refer to POWERTRAIN VERIFICATION TEST - 6.7L .
- CHECK THE (K824) 5-VOLT SUPPLY CIRCUIT FOR AN OPEN/HIGH RESISTANCE
- Measure the resistance of the (K824) 5-Volt Supply circuit between the PCM C1 harness connector and the CKP Sensor harness connector.
Is the resistance below 5.0 Ohms?
Yes
- Go To 4
No
- Repair the (K824) 5-Volt Supply circuit for an open or high resistance.
- Perform the POWERTRAIN VERIFICATION TEST - 6.7L. Refer to POWERTRAIN VERIFICATION TEST - 6.7L .
- Measure the resistance of the (K824) 5-Volt Supply circuit between the PCM C1 harness connector and the CKP Sensor harness connector.
- CHECK THE (K925) RETURN CIRCUIT FOR AN OPEN/HIGH RESISTANCE
- Measure the resistance of the (K925) CKP Return circuit between the PCM C1 harness connector and the CKP Sensor harness connector.
Is the resistance below 5.0 Ohms?
Yes
- Go To 5
No
- Repair the (K925) CKP Return circuit for an open or high resistance.
- Perform the POWERTRAIN VERIFICATION TEST - 6.7L. Refer to POWERTRAIN VERIFICATION TEST - 6.7L .
- Measure the resistance of the (K925) CKP Return circuit between the PCM C1 harness connector and the CKP Sensor harness connector.
- CHECK FOR THE (K24) SIGNAL CIRCUIT SHORTED TO THE (K925) RETURN CIRCUIT
- Measure the resistance between the (K24) CKP Signal circuit and the (K925) CKP Return circuit at the CKP Sensor harness connector.
Is the resistance below 10k Ohms?
Yes
- Repair the short between the (K24) CKP Signal circuit and the (K925) CKP Return circuit.
- Perform the POWERTRAIN VERIFICATION TEST - 6.7L. Refer to POWERTRAIN VERIFICATION TEST - 6.7L .
No
- Go To 6
- Measure the resistance between the (K24) CKP Signal circuit and the (K925) CKP Return circuit at the CKP Sensor harness connector.
- CHECK FOR THE (K24) SIGNAL CIRCUIT SHORTED TO THE (K824) 5-VOLT SUPPLY CIRCUIT
- Measure the resistance between the (K24) CKP Signal circuit and the (K824) 5-Volt Supply circuit in the CKP Sensor harness connector.
Is the resistance below 10k Ohms?
Yes
- Repair the short between the (K24) CKP Signal circuit and the (K824) 5-Volt Supply circuit.
- Perform the POWERTRAIN VERIFICATION TEST - 6.7L. Refer to POWERTRAIN VERIFICATION TEST - 6.7L .
No
- Go To 7
- Measure the resistance between the (K24) CKP Signal circuit and the (K824) 5-Volt Supply circuit in the CKP Sensor harness connector.
- CHECK THE (K24) SIGNAL CIRCUIT FOR A SHORT GROUND
- Measure the resistance between ground and the (K24) CKP Signal circuit at the CKP Sensor harness connector.
Is the resistance below 10k Ohms?
Yes
- Repair the (K24) CKP Signal circuit for a short to ground.
- Perform the POWERTRAIN VERIFICATION TEST - 6.7L. Refer to POWERTRAIN VERIFICATION TEST - 6.7L .
No
- Go To 8
- Measure the resistance between ground and the (K24) CKP Signal circuit at the CKP Sensor harness connector.
- CHECK THE CKP SENSOR
- Measure the resistance between the (K824) 5-Volt Supply circuit and the (K24) CKP Signal circuit through the CKP Sensor.
Is the resistance between 900 and 1100 Ohms?
Yes
- Go To 9
No
- Replace the CKP Sensor in accordance with the service information. Refer to SENSOR, CRANKSHAFT POSITION, REMOVAL .
- Perform the POWERTRAIN VERIFICATION TEST - 6.7L. Refer to POWERTRAIN VERIFICATION TEST - 6.7L .
- Measure the resistance between the (K824) 5-Volt Supply circuit and the (K24) CKP Signal circuit through the CKP Sensor.
- POWERTRAIN CONTROL MODULE
- Disconnect all PCM harness connectors.
- Disconnect all related in-line harness connections (if equipped).
- Disconnect the related component harness connectors.
- Inspect harness connectors, component connectors, and all male and female terminals for the following conditions:
- Proper connector installation.
- Damaged connector locks.
- Corrosion.
- Other signs of water intrusion.
- Weather seal damage (if equipped).
- Bent terminals.
- Overheating due to a poor connection (terminal may be discolored due to excessive current draw).
- Terminals that have been pushed back into the connector cavity.
- Perform a terminal drag test on each connector terminal to verify proper terminal tension.
Repair any conditions that are found.
- Reconnect all PCM harness connectors. Be certain that all harness connectors are fully seated and the connector locks are fully engaged.
- Reconnect all in-line harness connectors (if equipped). Be certain that all connectors are fully seated and the connector locks are fully engaged.
- Reconnect all related component harness connectors. Be certain that all connectors are fully seated and the connector locks are fully engaged.
- With the scan tool, erase DTCs.
- Using the recorded Freeze Frame and Environmental Data, along with the When Monitored and Set Conditions above, operate the vehicle in the conditions that set the DTC.
- With the scan tool, read PCM DTCs.
Did the DTC return?
Yes
- Replace the Powertrain Control Module (PCM) in accordance with the Service Information. Refer to MODULE, POWERTRAIN CONTROL, 6.7L DIESEL, REMOVAL .
- Perform the PCM VERIFICATION TEST. Refer to POWERTRAIN VERIFICATION TEST - 6.7L .
No
- Test complete.
- Perform the PCM VERIFICATION TEST. Refer to POWERTRAIN VERIFICATION TEST - 6.7L .