Diagnostic Test

WARNING: This page is about a different car, the 2014 RAM 1500. However, it is still accessible from the selected car via links, so may be relevant.
  1. ACTIVE DTC 
    1. Ignition on, engine not running.
    2. With the scan tool, select View DTCs.

      Is the DTC Active at this time?

      Yes 

      • Go To  2

      No 

      • Perform the INTERMITTENT CONDITION diagnostic procedure. Refer to INTERMITTENT DTC .
  2. EVP RELAY 
    1. Turn the ignition off.
    2. Measure the resistance of the EVP Relay Coil.
      NOTE:

      Measure across terminals 85 and 86 of the relay.

      Is the resistance between 60 to 80 Ohms?

      Yes 

      • Go To  3

      No 

      • Verify that there is good pin to terminal contact in the EVP Relay and Powertrain Control Module connectors. If OK, replace the EVP Relay.
      • Perform the POWERTRAIN VERIFICATION TEST. Refer to PCM VERIFICATION TEST .
  3. CHECK THE (T110) EVP RELAY CONTROL CIRCUIT FOR A SHORT TO VOLTAGE 
    1. Disconnect the PDC C3 harness connector.
    2. Turn the ignition on.
    3. Measure the (T110) EVP Relay Control circuit for voltage at the PDC C3 harness connector.

      Is there voltage present?

      Yes 

      • Repair the (T110) EVP Relay Control circuit for a short to voltage.
      • Perform the POWERTRAIN VERIFICATION TEST. Refer to PCM VERIFICATION TEST .

      No 

      • Go To  4
  4. POWER DISTRIBUTION CENTER 
    1. Turn the ignition off.
    2. Reconnect the PDC C3 harness connector.
    3. Turn the ignition on.
    4. Measure the (T110) EVP Relay Control circuit for voltage at the EVP Relay.

      Is there voltage present?

      Yes 

      • Replace the Power Distribution Center in accordance with the service information.
      • Perform the POWERTRAIN VERIFICATION TEST. Refer to PCM VERIFICATION TEST .

      No 

      • Go To  5.
  5. POWERTRAIN CONTROL MODULE (PCM) 
    1. Using the wiring diagram/schematic as a guide, inspect the wiring and connectors between the Electric Vacuum Pump, PDC and the Powertrain Control Module (PCM).
    2. Look for any chafed, pierced, pinched or partially broken wires.
    3. Look for broken, bent, pushed out or corroded terminals.
    4. Monitor the scan tool data relative to this circuit and wiggle test the wiring and connectors.
    5. Look for the data to change or for the DTC to reset during the wiggle test.
    6. Perform any Technical Service Bulletins that may apply.

      Were any problems found?

      Yes 