INSTALLATION





1. Position new gasket on left maniverter and install the bolts.
2. Tighten the maniverter bolts to 23 N.m (200 in. lbs.)
3. Position cross-over pipe to the maniverter connections.

NOTE: Verify that there is at least 16 mm of clearance between the indentation in the cross under pipe near the extension pipe flange and the fore-aft crossmember. Otherwise, the cross under pipe can contact the fore-aft crossmember due to engine torquing, causing a noise/vibration during acceleration.

4. Position new gasket on right exhaust manifold and install the bolts. Tighten bolts to 23 N.m (200 in. lbs.)
5. Install and tighten crossover pipe bolts to 41 Nm (30 ft. lbs.).