Diagnostic Test
- ACTIVE DTC
- Ignition on, engine not running.
- With a scan tool, read DTCs.
Is the DTC active at this time?
Yes
- Go to step 2
No
- Refer to the INTERMITTENT CONDITION Diagnostic Procedure.
- Perform the POWERTRAIN VERIFICATION TEST. See DTC-Based Diagnostics/MODULE, Powertrain Control (PCM) - Standard Procedure
- BRAKE LAMP SWITCH OPERATION
- Turn the ignition off.
- Remove the Brake Lamp Switch and disconnect the harness connector.
- Measure the resistance between the (Z902) Ground circuit terminal and the (B15) Brake Lamp Switch Signal terminal at the Brake Lamp Switch.
- Apply and release the brake pedal plunger while monitoring the ohmmeter.
Does the resistance change from below 5.0 ohms to an open circuit?
Yes
- Go To step 3
No
- Replace the Brake Lamp Switch.
- Perform the POWERTRAIN VERIFICATION TEST. See DTC-Based Diagnostics/MODULE, Powertrain Control (PCM) - Standard Procedure
- (B15) BRAKE LAMP SWITCH SIGNAL CIRCUIT SHORT TO GROUND
- Disconnect the PCM harness connectors.
- Measure the resistance between ground and the (B15) Brake Lamp Switch Signal circuit in the Brake Lamp Switch harness connector.
Is the resistance below 100 ohms?
Yes
- Repair the short to ground in the (B15) Brake Lamp Switch Signal circuit.
- Perform the POWERTRAIN VERIFICATION TEST. See DTC-Based Diagnostics/MODULE, Powertrain Control (PCM) - Standard Procedure
No
- Go To step 4
- PCM NOTE: Before continuing, check the PCM harness connector terminals for corrosion, damage, or terminal push out. Repair as necessary.
- Using the schematics as a guide, inspect the wire harness and connectors. Pay particular attention to all Power and Ground circuits.
If there are no possible causes remaining, view repair.
Repair
- Replace and program the Powertrain Control Module in accordance with the Service Information.
- Perform the POWERTRAIN VERIFICATION TEST. See DTC-Based Diagnostics/MODULE, Powertrain Control (PCM) - Standard Procedure
- Using the schematics as a guide, inspect the wire harness and connectors. Pay particular attention to all Power and Ground circuits.