Diagnostic Test

WARNING: This page is about a different car, the 2006 Dodge Magnum, 2006 Dodge Charger, and 2006 Chrysler 300. However, it is still accessible from the selected car via links, so may be relevant.
  1. 1)  NVLD SWITCH OPERATION 

    Start the engine.

    Allow the engine to idle.

    Using a scan tool, perform the NVLD FORCED MONITOR TEST.

    Monitor the NVLD Switch state.

    NOTE: As the test runs, the NVLD Switch should go from an OPEN state to a CLOSED state and then return to OPEN when the test is complete.

    Did the NVLD Switch operate as described above? 

    Yes 

    1. Refer to INTERMITTENT CONDITION .
    2. Perform POWERTRAIN VERIFICATION TEST .

    No 

    1. Go To  2).
  2. 2)  NVLD ASSEMBLY 
    Fig 1: Checking NVLD Switch Signal Circuit & Ground Circuit
    GC0014985Courtesy of DAIMLERCHRYSLER CORP.

    Turn the ignition off.

    Disconnect the NVLD electrical harness connector.

    Ignition on, engine not running.

    Monitor the NVLD Switch state on the scan tool.

    Connect a jumper wire between the (K107) NVLD Switch Signal circuit and the (Z914) Ground circuit in the NVLD harness connector.

    Does the Switch change from OPEN to CLOSED with the jumper wire installed? 

    Yes 

    1. Replace the NVLD Assembly.
    2. Perform POWERTRAIN VERIFICATION TEST .

    No 

    1. Go To  3).
      NOTE: Remove the jumper wire before continuing.
  3. 3)  (K107) NVLD SWITCH SIGNAL CIRCUIT SHORTED TO BATTERY VOLTAGE 
    Fig 2: Checking NVLD Switch Signal Circuit
    GC0014994Courtesy of DAIMLERCHRYSLER CORP.

    1

    Turn the ignition off.

    Disconnect the C3 PCM harness connector.

    Ignition on, engine not running.

    Measure the voltage on the (K107) NVLD Switch Signal circuit in the NVLD electrical harness connector.

    Is the voltage above 0 volts? 

    Yes 

    1. Repair the short to battery voltage in the (K107) NVLD Switch Signal circuit.
    2. Perform POWERTRAIN VERIFICATION TEST .

    No 

    1. Go To  4).
  4. 4)  (K107) NVLD SWITCH SIGNAL CIRCUIT OPEN 
    Fig 3: Checking NVLD Switch Signal Circuit
    GC0014987Courtesy of DAIMLERCHRYSLER CORP.

    Turn the ignition off.

    CAUTION: Do not probe the PCM harness connectors. Probing the PCM harness connectors will damage the PCM terminals resulting in poor terminal to pin connection. Install Miller Special Tool #8815 to perform diagnosis.

    Measure the resistance of the (K107) NVLD Switch Signal circuit from the NVLD electrical harness connector to the appropriate terminal of special tool #8815.

    Is the resistance below 5.0 ohms? 

    Yes 

    1. Go To  5).

    No 

    1. Repair the open in the (K107) NVLD Switch Signal circuit.
    2. Perform POWERTRAIN VERIFICATION TEST .
  5. 5)  (K107) NVLD SWITCH SIGNAL CIRCUIT SHORTED TO THE (K106) NVLD SOLENOID CONTROL CIRCUIT 
    Fig 4: Checking NVLD Switch Signal Circuit & Solenoid Control Circuit
    GC0014995Courtesy of DAIMLERCHRYSLER CORP.

    Measure the resistance between the (K107) NVLD Switch Signal circuit and the (K106) NVLD Solenoid Control circuit in the NVLD electrical harness connector.

    Is the resistance below 5.0 ohms? 

    Yes 

    1. Repair the short between the (K107) NVLD Switch Signal circuit and the (K106) NVLD Solenoid Control circuit.
    2. Perform POWERTRAIN VERIFICATION TEST .

    No 

    1. Go To  6).
  6. 6)  (Z914) GROUND CIRCUIT OPEN 
    Fig 5: Checking NVLD Solenoid Ground Circuit
    GC0014986Courtesy of DAIMLERCHRYSLER CORP.

    Measure the resistance between the (Z914) Ground circuit and ground.

    Is the resistance below 5.0 ohms? 

    Yes 

    1. Go To  7).

    No 

    1. Repair the open in the (Z914) Ground circuit.
    2. Perform POWERTRAIN VERIFICATION TEST .
  7. 7)  PCM 
    NOTE: Before continuing, check the PCM harness connector terminals for corrosion, damage, or terminal push out. Repair as necessary.

    Using the schematics as a guide, inspect the wire harness and connectors. Pay particular attention to all Power and Ground circuits.

    Were there any problems found? 

    Yes 

    1. Repair as necessary.
    2. Perform POWERTRAIN VERIFICATION TEST .

    No 

    1. Replace and program the Powertrain Control Module per Service Information.
    2. Perform POWERTRAIN VERIFICATION TEST .