Installation - 5.7L

WARNING: This page is about a different car, the 2010 Dodge Charger and 2010 Chrysler 300. However, it is still accessible from the selected car via links, so may be relevant.
Fig 1: Short Runner Valve Actuator Rubber O-Ring Seal
GC0118917Courtesy of CHRYSLER LLC
  1. Install a new short runner valve actuator rubber O-ring seal (1).
    Fig 2: Short Runner Valve Actuator Retaining Bolts
    GC0118916Courtesy of CHRYSLER LLC
  2. Position the short runner valve actuator, install the retaining bolts (1) and tighten to 5 N.m (44 in. lb.).
    Fig 3: Intake Manifold Retaining Bolt Removal & Tightening Sequence
    GC0088124Courtesy of CHRYSLER LLC
  3. Install the intake manifold and throttle body as an assembly. Refer to Engine/Manifolds/MANIFOLD, Intake - Installation .
    Fig 4: Battery
    GC0087848Courtesy of CHRYSLER LLC
  4. Connect the negative battery cable (1).