Pinion Depth Measurement

WARNING: This page is about a different car, the 2008 Dodge Magnum, 2008 Dodge Charger, and 2008 Chrysler 300. However, it is still accessible from the selected car via links, so may be relevant.

Pinion depth measurement is taken with the pinion head and tail bearing cups pressed into the axle housing without the shim.

Fig 1: Installing Pinion Head Bearing Cup
GC0014246Courtesy of CHRYSLER LLC
  1. Press pinion head bearing cup into housing using Handle C-4171 (1) and Installer C-4310 (2).
    Fig 2: Installing Pinion Tail Bearing Cup
    GC0014247Courtesy of CHRYSLER LLC
  2. Press pinion tail bearing cup into housing using Handle C-4171 (1) and Installer D-146 (2).
    Fig 3: L-Block, Gage Block & Bearing
    GC0014248Courtesy of CHRYSLER LLC
  3. Assemble Pinion Height Block 6739 (3), Pinion Head Bearing Cone (1), Screw 6741 (all these can be found in a Pinion Gauge Set such as 6774), and Pinion Height Gage Block 9085 (2). Install assembly into axle housing and through bearing cups.
    Fig 4: Pinion Depth Gauge Tools - Typical
    GC0014256Courtesy of CHRYSLER LLC
  4. Install pinion tail bearing and Cone 6740 (4). Tighten Cone 6740 by hand until 3.4 N.m (30 in. lbs.) of rotating torque is measured at Screw 6741 (5).
    Fig 5: Removing/Installing Arbor Discs
    GC0014259Courtesy of CHRYSLER LLC
  5. Install Arbor Discs 9083 (1).
    Fig 6: Removing/Installing Arbor Bar
    GC0014258Courtesy of CHRYSLER LLC
  6. Install Arbor Bar D-115-3 (1) from a Pinion Gauge Set such as 6774.
    Fig 7: Pinion Gage Setup
    GC0014257Courtesy of CHRYSLER LLC
  7. Verify pinion depth setup is as shown.
    Fig 8: Indicator/Scooter Block Setup
    GC0014249Courtesy of CHRYSLER LLC
  8. Install Dial Indicator 9524 (1) to Scooter Block D-115-2A (2) (from a Pinion Gauge Set such as 6774). Secure with set-screw (3).
    Fig 9: Zero Dial Indicator on L-Block
    GC0014250Courtesy of CHRYSLER LLC
  9. Install Indicator/Block assembly to top of Height Block 6739 (1). Zero indicator on top surface.
    Fig 10: Measuring Arbor Bar
    GC0014251Courtesy of CHRYSLER LLC
  10. Slide indicator probe off of height block and onto Arbor Bar D-115-3 (2). As indicator contacts Arbor Bar (2), indicator needle will rotate clockwise. Continue moving indicator probe to the crest of the arbor bar and record the highest reading.
    Fig 11: Pinion Gear Face Etchings
    GC0014339Courtesy of CHRYSLER LLC
  11. Select a shim equal to the dial indicator reading plus the drive pinion gear depth variance number etched into the pinion face (1). For example, if the depth variance is -01, subtract 0.01 mm (0.0004 in.) from dial indicator reading.
    Fig 12: Removing Pinion Head Bearing Cup
    GC0014252Courtesy of CHRYSLER LLC
  12. Using Handle C-4171 (2) and Remover 9084 (1), drive out pinion head bearing cup and insert specified shim.