Home >> Chrysler >> 2006 >> PT Cruiser Base, 2D Convertible, Standard >> Repair and Diagnosis >> External Pages >> Different car >> Section 61 ((40TE & 41TE Automatic Transmission - Electrical Diagnostics)) >> Automatic - 40/41TE >> DTC Troubleshooting >> P1775-Solenoid Switch Valve Latched In TCC Position >> Diagnostic Test

Diagnostic Test

WARNING: This page is about a different car, the 2007 Chrysler PT Cruiser. However, it is still accessible from the selected car via links, so may be relevant.
  1. 1) DETERMINING IF RELATED DTCS ARE PRESENT 

    With the scan tool, check for other Transmission DTCs

    Is the DTC P0841 present also? 

    Yes 

    1. Refer to the applicable Transmission Information and perform the appropriate diagnostic procedure(s).

    No 

    1. Go to  2).
  2. 2) CHECK TO SEE IF DTC P1775 IS CURRENT 

    With the scan tool, view DTCs.

    Is the status Active for this DTC or is the STARTS SINCE SET counter 2 or less? 

    Yes 

    1. Go to  3).

    No 

    1. Go to  8).
  3. 3) PCM AND WIRING 

    Turn the ignition off to the lock position.

    Remove the Ignition Switch Feed fuse from the TIPM.

    CAUTION: Removal of the Ignition Switch Feed fuse from the TIPM will prevent the vehicle from being started in gear.
    WARNING: The Ignition Switch Feed fuse must be removed from the TIPM. Failure to do so can result in personal injury or death.

    Install the Transmission Simulator, Miller tool #8333 and the Electronic Transmission Adapter kit.

    Ignition on, engine not running.

    With the Transmission Simulator, turn the Pressure Switch selector switch to L/R.

    With the scan tool, monitor the L/R Pressure Switch State while pressing the Pressure Switch Test button.

    Did the Pressure Switch state change from open to closed when the test button was pressed? 

    Yes 

    1. Repair internal transmission as necessary per the Service Information. Inspect the Solenoid Switch Valve per the Service Information and repair or replace as necessary. If no problems are found, replace the Transmission Solenoid/Pressure Switch Assembly.
    2. Perform 40/41TE TRANSMISSION VERIFICATION TEST .

    No 

    1. Go to  4).
  4. 4) (T16) TRANSMISSION CONTROL OUTPUT CIRCUIT OPEN 
    Fig 1: Checking Transmission Control Circuit With 12-Volt Test Light
    GC0041062Courtesy of CHRYSLER LLC

    Turn the ignition off to the lock position.

    Disconnect the Transmission Solenoid/Pressure Switch Assembly harness connector.

    Disconnect the PCM C4 harness connector.

    CAUTION: Do not probe the PCM harness connectors. Probing the PCM harness connectors will damage the PCM terminals resulting in poor terminal to pin connection. Install Miller Special Tool #8815 to perform diagnosis.

    Ignition on, engine not running.

    With the scan tool in the TIPM, actuate the TCM output.

    Using a 12-volt test light connected to ground, check all (T16) Transmission Control Output circuits in the appropriate terminals of Miller tool #8815.

    NOTE: The test light must illuminate brightly. Compare the brightness to that of a direct connection to the battery.

    Does the test light illuminate brightly on all Transmission Control Relay Output circuits? 

    Yes 

    1. Repair the (T16) Transmission Control Output circuit for an open.
    2. Perform 40/41TE TRANSMISSION VERIFICATION TEST .

    No 

    1. Go to  5).
  5. 5) (T50) L/R PRESSURE SWITCH SENSE CIRCUIT OPEN 
    Fig 2: Checking L/R Pressure Switch Sense Circuit For An Open
    GC0041056Courtesy of CHRYSLER LLC

    Measure the resistance of the (T50) L/R Pressure Switch Sense circuit between the Transmission Solenoid/Pressure Switch Assembly harness connector and the appropriate terminal of Miller tool #8815.

    Is the resistance above 5.0 ohms? 

    Yes 

    1. Repair the (T50) L/R Pressure Switch Sense circuit for an open.
    2. Perform 40/41TE TRANSMISSION VERIFICATION TEST .

    No 

    1. Go to  6).
  6. 6) (T50) L/R PRESSURE SWITCH SENSE CIRCUIT SHORT TO GROUND 
    Fig 3: Checking L/R Pressure Switch Sense Circuit For A Short To Ground
    GC0041057Courtesy of CHRYSLER LLC

    Measure the resistance between ground and the (T50) L/R Pressure Switch Sense circuit.

    Is the resistance below 5.0 ohms? 

    Yes 

    1. Repair the (T50) L/R Pressure Switch Sense circuit for a short to ground.
    2. Perform 40/41TE TRANSMISSION VERIFICATION TEST .

    No 

    1. Go to  7).
  7. 7) (T50) L/R PRESSURE SWITCH SENSE CIRCUIT SHORT TO VOLTAGE 
    Fig 4: Checking L/R Pressure Switch Sense Circuit For Short To Voltage
    GC0041058Courtesy of CHRYSLER LLC

    Ignition on, engine not running.

    While still actuating the TCM output in the TIPM with the scan tool, measure the voltage of the (T50) L/R Pressure Switch Sense circuit.

    Is the voltage above 0.5 volts? 

    Yes 

    1. Repair the (T50) L/R Pressure Switch Sense circuit for a short to voltage.
    2. Perform 40/41TE TRANSMISSION VERIFICATION TEST .

    No 

    1. Using the schematics as a guide, check the Powertrain Control Module (PCM) terminals for corrosion, damage or terminal push out. Pay particular attention to all power and ground circuits. Check for Service Information Tune-ups or Service Bulletins for any possible causes that may apply. If no problems are found, replace and program the PCM per the Service Information. With the scan tool, perform QUICK LEARN.
    2. Perform 40/41TE TRANSMISSION VERIFICATION TEST .
  8. 8) INTERMITTENT WIRING AND CONNECTORS 

    The conditions necessary to set this DTC are not present at this time.

    Test drive and verify if the transmission is launching in 2nd gear and/or no TCC engagement.

    With the scan tool, check the DTC EVENT DATA to help identify the conditions in which the DTC was set.

    Are there 2nd gear launches and/or no TCC engagement? 

    Yes 

    1. Disassemble and inspect the Valve Body per the Service Information and repair or replace as necessary. If no problems are found in the Valve Body, replace the Transmission Solenoid Pressure Switch Assembly.
    2. Perform 40/41TE TRANSMISSION VERIFICATION TEST .

    No 

    1. Test Complete.