Installation Procedure
WARNING: This page is about a different variant/trim than selected.
-
Courtesy of GENERAL MOTORS COMPANY
Positive Crankcase Ventilation Valve Seal- Upperand - Lower (1, 2) - Install NEW [2x]
- Positive Crankcase Ventilation Oil Separator (3) - Install
- Positive Crankcase Ventilation Oil Separator Bolt (4) - Install and tighten in sequence [7x] 10 N.m (89 lb in)
- Water Outlet - Install - Water Outlet Replacement (LGX)
- Fuel Injection Fuel Rail Assembly - Install - Fuel Injection Fuel Rail Assembly Replacement - Bank 2
- Fuel Injection Fuel Rail Assembly - Install - Fuel Injection Fuel Rail Assembly Replacement - Bank 1
NOTE:
This component has tamper-proof connections and cannot be disassembled.