Installation Procedure
WARNING: This page is about a different variant/trim than selected.
- CAUTION:
Transmission Fluid Pressure Switch (1) - Install and tighten to 4 N.m (35 lb in)
Connect the fluid pressure switch connector (2).
- Install the 2 fluid pressure switch harness bracket bolts (1) and tighten to 8 N.m (71 lb in)
Install the NEW O-ring (1) to the fluid strainer.
Install the fluid strainer (2) to the control valve body.
- Install the 3 fluid strainer mounting bolts (1) and tighten to 8 N.m (71 lb in)
- Control Valve Body Cover @ Transmission - Install - Control Valve Body Cover Replacement
- Connect the battery negative cable. Battery Negative Cable Disconnection and Connection
- Fill the transmission fluid. Transmission Fluid Drain and Fill (Maintenance) Transmission Fluid Drain and Fill (Repair)