Circuit/System Testing
WARNING: This page is about a different variant/trim than selected.
- Ignition OFF, disconnect the harness connector at the Q22 Intake Manifold Tuning Solenoid Valve.
- Ignition OFF and all vehicle systems OFF. It may take up to 2 min for all vehicle systems to power down. Test for less than 5 Ω between the ground circuit terminal 2 and ground.
- If greater than the specified range, test the ground circuit for an open/high resistance.
- Ignition ON, verify a test lamp illuminates between the ignition voltage circuit terminal 1 and ground.
- If the test lamp does not illuminate, test the ignition voltage circuit for a short to ground or an open/high resistance.
- If the circuit tests normal and the ignition voltage circuit fuse is open, test all components connected to the ignition voltage circuit replace as necessary.
- Ignition OFF, test for less than 0.3 V between the control circuit terminal 3 and ground.
- If greater than the specified range, test the control circuit for a short to voltage. If the circuit tests normal, replace the K20 Engine Control Module.
- Ignition ON, test for 4.8-5.2 V between the signal circuit terminal 4 and ground.
- If less than the specified range, test the signal circuit for a short to ground or an open/high resistance. If the circuit tests normal, replace the K20 Engine Control Module.
- If greater than the specified range, test the signal circuit for a short to voltage. If the circuit tests normal, replace the K20 Engine Control Module.
- If all circuits test normal, test or replace the Intake Manifold.