Installation Procedure
WARNING: This page is about a different variant/trim than selected.
- Install a NEW gasket onto the AIR pipe studs.
- Position and install the AIR check valve.
- Install the AIR shutoff/check valve bolts (2).
Tighten: Tighten the bolts to 50 N.m (37 lb ft).
- Raise and support the vehicle.
- Install the AIR shutoff/check valve nuts (1).
Tighten: Tighten the nuts to 10 N.m (89 lb in).
- Lower the vehicle.
- Connect the engine wiring harness electrical connector (2) to the AIR shutoff/check valve.
- Connect the AIR feed tube quick connect fitting (1) to the AIR shutoff/check valve. Refer to Plastic Collar Quick Connect Fitting Service .
- Install the AIR feed tube bolt (3) to the heater inlet/outlet pipe bracket.
Tighten: Tighten the bolt to 10 N.m (89 lb in).
- Install the exhaust crossover pipe. Refer to Exhaust Crossover Pipe Replacement (LZE/LZ4/LGD) .
CAUTION:
Refer to Fastener Caution
.