Circuit/System Testing
WARNING: This page is about a different variant/trim than selected.
P0451 and P0454
- Start the engine with the J 41413-200 connected to the fuel filler neck.
- Allow the engine to idle.
- Use the Purge/Seal function to seal the system with a scan tool.
- Command the EVAP canister purge solenoid valve to 30 percent.
- Observe the vacuum/pressure gage on the J 41413-200 and the FTP parameter on the scan tool.
- Allow the vacuum to increase on the gage of the J 41413-200 until it reaches approximately 16 inches H2O, or until the vacuum reached the abort limit on the scan tool.
- Use the Purge/Seal function to seal the system with a scan tool.
- If the difference between the FTP parameter on a scan tool and the vacuum/pressure gage on the J 41413-200 is more than 1 inch H2O, replace the FTP sensor.
- If the Fuel Tank Pressure Sensor parameter on a scan tool display is less than 3.2 volts, replace the FTP sensor.
IMPORTANT:
Refer to the J 41413-200
operation manual for detailed instructions.
P0452 and P0453
- If DTC P0641 is set, repair that DTC first.
- With the ignition OFF, disconnect the harness connector at the FTP sensor.
- With the ignition ON, the scan tool FTP parameter should indicate 0 volts.
- If the parameter is more than 0 volts, test for unexpected voltage on the circuit or a faulty control module.
- With the ignition ON, measure for 4.8-5.2 volts between the 5-volt reference circuit of the FTP sensor and ground.
- If over 5.2 volts, test for unexpected voltage at the circuit or faulty control module.
- If under 4.8 volts, test for a short to ground, open/high resistance at the circuit or faulty control module.
- With the ignition ON, measure for less than 5 ohms of resistance between the low reference circuit of the FTP sensor and a good ground.
- If greater than 5 ohms, test for an open/high resistance in the circuit or faulty control module.
- With the ignition ON, the scan tool FTP sensor parameter should indicate 4.8-5.2 volts with a 3-amp fused jumper wire connecting the FTP signal circuit to the 5-volt reference circuit.
- If under 4.8 volts, test for a short to ground or an open at the circuit or a faulty control module.
- If the circuits and control module test OK then replace the FTP sensor.