Installation Procedure
WARNING: This page is about a different variant/trim than selected.
- Clean the cylinder head gasket surfaces on the engine block.
- Inspect the dowel pins (cylinder head locator) for proper installation.
- Clean the cylinder head gasket surfaces on the cylinder head.
- Install the NEW cylinder head gasket in position over the dowel pins cylinder head locator.
- Install the cylinder head onto the engine block.
Guide the cylinder head carefully into place over the dowel pins and the cylinder head gasket.
- Apply sealant GM P/N 12346004 (Canadian P/N 12346004) or equivalent to the threads of the cylinder head bolts.
- Install the cylinder head bolts finger tight.
- Tighten the cylinder head bolts in sequence on the first pass.
Tighten: Tighten the bolts in sequence on the first pass to 30 N.m (22 lb ft).
- Using theJ 45059
tighten the cylinder head bolts in sequence on the final pass. See Special Tools .
Tighten:
- Tighten the long bolts (1, 4, 5, 8, and 9) on the final pass in sequence to 75 degrees.
- Tighten the medium bolts (12 and 13) on the final pass in sequence to 65 degrees.
- Tighten the short bolts (2, 3, 6, 7, 10, and 11) on the final pass in sequence to 55 degrees.
- Install the spark plug wire support and bolts.
Tighten: Tighten only the rear spark plug wire support bolt to 12 N.m (106 lb in).
- Remove the front spark plug wire support bolt.
The front spark plug wire support bolt is used to fasten the oil level indicator tube, and will be installed within the oil level indicator tube installation procedure.
- Measure the NEW spark plugs for the proper gap.
Adjust the spark plug gap if necessary.
Specification: Spark plug gap to 1.52 mm (0.060 in).
- Install the spark plugs.
Tighten:
- Tighten the spark plugs for a USED cylinder head to 15 N.m (11 lb ft).
- Tighten the spark plugs for the initial installation of a NEW cylinder head to 30 N.m (22 lb ft).
- Install the valve pushrods. Refer to Valve Rocker Arm and Push Rod Replacement .
- Install the ground wires and nut at the rear of the cylinder head.
Tighten: Tighten the ground wire nut to 10 N.m (88 lb in).
- Install the exhaust manifold. Refer to Exhaust Manifold Replacement - Right (4.3L) or Exhaust Manifold Replacement - Right (4.8L, 5.3L, 6.0L) in Engine Exhaust.
- Install the intake manifold. Refer to Intake Manifold Replacement - Lower .
- Install the stud for the generator mounting bracket to the cylinder head.
Tighten: Tighten the generator mounting bracket stud to 20 N.m (15 lb ft).
- Install the generator mounting bracket. Refer to Generator Bracket Replacement (4.8L, 5.3L, and 6.0L) in Engine Electrical.
- Install the fan shroud. Refer to Fan Shroud Replacement - Upper and to Fan Shroud Replacement - Lower in Engine Cooling.
- Fill the engine coolant system. Refer to Draining and Filling Cooling System in Engine Cooling.
- Connect the battery negative cable. Refer to Battery Negative Cable Disconnect/Connect Procedure in Engine Electrical.
- Install the engine cover. Refer to Engine Cover Replacement in Interior Trim.
IMPORTANT:
Do not use any type sealer on the cylinder head gasket, unless specified.
NOTE:
Refer to Fastener Notice
in Cautions and Notices.